§ 01

Permit authority

Code Enforcement Office

Street address
New Town Hall, 10 Fairway Lane, Frye Island, ME (mailing address through town office)
Coverage
Town of Frye Island municipal limits. Frye Island is a seasonal island community accessible by ferry on Sebago Lake. CEO available Tuesdays and Thursdays 8:00 am to 2:30 pm. Tree Removal Permit required for trees over 4 inches in diameter.
Online portal
Permit Portal
Additional resources
§ 02

When a permit is required

Permit triggers and exempt work for Frye Island

For all new construction, structural alterations, additions, demolition. Tree Removal Permit required for any tree removed over 4 inches in diameter. Shoreland zoning applies given island location.

Ordinary maintenance not involving structural change
Painting and similar finish work
  • Exempt Ordinary maintenance not involving structural change
  • Exempt Painting and similar finish work

Note: Note: Tree removal of trees over 4 inches in diameter requires a permit (more restrictive than standard MUBEC). Refer to fryeislandtown.org for full ordinance list.

Required documents
  • Completed application, site plan, construction drawings
  • energy compliance documentation.
Building code
MUBEC; 2021 I-codes effective April 7, 2025.
Owner-builder
Not detailed; contact CEO.
Contractor requirements
State-licensed electrician and plumber required.
§ 03

Application process

Application → plan check → issuance → inspection → final

  1. 01
    Download permit application from fryeislandtown.org/code-enforcement/page/permit-applications.
  2. 02
    Complete application; determine project type (building, shoreland use, plumbing, septic, tree removal, solar, sign, etc.).
  3. 03
    Submit completed application in drop box at 10 Fairway Lane or email to codeenforcement@fryeislandtown.org.
  4. 04
    CEO contacts applicant with fee amount.
  5. 05
    Pay fee by check (payable to "Town of Frye Island"; note purpose in memo), in-person, drop box, or online via credit card/ACH (2.5% processing fee or $2.95 flat rate ACH).
  6. 06
    CEO reviews application; impact fee may apply for new dwelling units (approved February 2024).
  7. 07
    Permit issued; post at job site.
  8. 08
    Schedule inspections.
  9. 09
    Final inspection and close-out.

Source: Code Enforcement Office ↗

§ 04

Required inspections

Scheduling and sequence

How to schedule
  • (207) 693-2150 (phone)
  • codeenforcement@fryeislandtown.org (email)
Inspection hours
CEO available Tuesdays and Thursdays 8:00 am to 2:30 pm

Typical sequence: Foundation, framing, rough-in trades, insulation, final

Contact CEO.

Source: Code Enforcement Office ↗

§ 05

Frequently asked

Common questions about Frye Island permits

01 Do I need a building permit in Frye Island, ME?
For all new construction, structural alterations, additions, demolition. Tree Removal Permit required for any tree removed over 4 inches in diameter. Shoreland zoning applies given island location.
02 How do I apply for a building permit in Frye Island, ME?
To apply for a building permit in Frye Island, ME, follow these steps: 1. Download permit application from fryeislandtown.org/code-enforcement/page/permit-applications. 2. Complete application; determine project type (building, shoreland use, plumbing, septic, tree removal, solar, sign, etc.). 3. Submit completed application in drop box at 10 Fairway Lane or email to codeenforcement@fryeislandtown.org. 4. CEO contacts applicant with fee amount. 5. Pay fee by check (payable to "Town of Frye Island"; note purpose in memo), in-person, drop box, or online via credit card/ACH (2.5% processing fee or $2.95 flat rate ACH). 6. CEO reviews application; impact fee may apply for new dwelling units (approved February 2024). 7. Permit issued; post at job site. 8. Schedule inspections. 9. Final inspection and close-out.
03 What work is exempt from building permits in Frye Island, ME?
Not all construction work requires a permit in Frye Island, ME. The following work is generally exempt: Ordinary maintenance not involving structural change; Painting and similar finish work. Note: Note: Tree removal of trees over 4 inches in diameter requires a permit (more restrictive than standard MUBEC). Refer to fryeislandtown.org for full ordinance list. When in doubt, confirm with the local building department before starting work.
04 How do I schedule a building inspection in Frye Island, ME?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Frye Island, ME via: (207) 693-2150, codeenforcement@fryeislandtown.org.
last verified April 2026 source Code Enforcement Office ↗ entry id permits/maine/cumberland/frye-island

Educational reference. Permit rules and fees change — confirm current requirements directly with Code Enforcement Office before applying. Jaspector is not legal advice.