When a permit is required
Permit triggers and exempt work for Vershire
Permits required for new driveways, subdivisions, all new buildings (including additions such as porches, decks, dormers, and all outbuildings). The Vershire Development Ordinance regulates building placement, dimensions, lot sizes, and use.
- Exempt Agricultural structures (with notification)
- Exempt Ordinary maintenance
Note: Consult the Vershire Development Ordinance and the Zoning Administrator for the current exemption list.
- Completed permit application
- Site plan or sketch
- Fee payment
- Building code
- Vershire Development Ordinance (adopted March 2008; check for amendments); 2025 Vermont Fire and Building Safety Code (DFS); 2024 Vermont RBES
- Permit validity
- Vermont statute: two-year commencement, three-year substantial completion. Confirm with Town Office.
- Owner-builder
- Vermont allows owner-builders.
- Contractor requirements
- No state general contractor license; electricians and plumbers must be Vermont state-licensed.
Source: Town of Vershire Town Office / Zoning Administrator ↗
Application process
Typical processing: 30 days from receipt of a complete application (Vermont statute requirement)
- 01 Determine whether a permit is required under the Vershire Development Ordinance. Contact the Town Office at 802-685-2227.
- 02 Download permit application forms from https://vershirevt.org/documents/ or pick up at the Town Office.
- 03 Complete the application; include a site plan or sketch showing property boundaries, the location of the proposed work, and relevant setbacks.
- 04 Submit the completed application to the Town Office with applicable fees.
- 05 The Zoning Administrator reviews the application; final boundary determinations must be obtained from the Zoning Administrator.
- 06 Upon approval, permit is issued. Post on property before commencing work.
- 07 For commercial/public buildings, also apply for DFS state construction permit.
Typical processing time: 30 days from receipt of a complete application (Vermont statute requirement)
Source: Town of Vershire Town Office / Zoning Administrator ↗
Required inspections
Scheduling and sequence
- 802-685-2227 (phone)
- Inspection hours
- Contact Town Office for current hours
Typical sequence: DFS inspections for commercial/public buildings: contact DFS at 802-479-7561
Frequently asked
Common questions about Vershire permits
01 Do I need a building permit in Vershire, VT? ▸
02 How do I apply for a building permit in Vershire, VT? ▸
03 How long does it take to get a building permit in Vershire, VT? ▸
04 What work is exempt from building permits in Vershire, VT? ▸
05 How do I schedule a building inspection in Vershire, VT? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with Town of Vershire Town Office / Zoning Administrator before applying. Jaspector is not legal advice.