When a permit is required
Permit triggers and exempt work for Braintree
All land development requiring a zoning permit under the Braintree Unified Bylaw: new construction, additions, alterations, change of use, subdivisions, boundary line adjustments.
- Exempt Agricultural structures (with notification)
- Exempt Ordinary maintenance/repair
Note: Consult Zoning Administrator for the full current exemption list per Braintree Unified Bylaw and Vermont law.
- Completed application
- Site plan
- Fee payment
- Specific additional materials for subdivision, conditional use, variance, or site plan review
- Building code
- Braintree Unified Bylaw (adopted March 2010; updated July 2025); 2025 Vermont Fire and Building Safety Code (DFS); 2024 Vermont RBES
- Permit validity
- Vermont statute: two-year commencement, three-year substantial completion. Confirm with Zoning Administrator.
- Owner-builder
- Vermont allows owner-builders. State trade licenses required for electrical and plumbing.
- Contractor requirements
- No state general contractor license; electricians and plumbers must be Vermont state-licensed.
Application process
Typical processing: 30 days from receipt of a complete application (Vermont statute requirement)
- 01 Review the Braintree Unified Bylaw to determine if a permit is required: https://braintreevt.gov/wp-content/uploads/2025/07/btunifiedbylaw-Approved3-4-10.pdf (updated July 2025).
- 02 Download the applicable permit application from https://braintreevt.gov/forms-applications/ (options: Zoning Permit, Minor Subdivision Permit, Major Subdivision Permit, Boundary Line Adjustment Permit, Certificate of Occupancy, Conditional Use Review, Variance Request, Waiver Request, Site Plan Review).
- 03 Complete the application fully.
- 04 Determine applicable fees from the Braintree Zoning Fee Schedule (effective August 5, 2025): https://braintreevt.gov/wp-content/uploads/2025/08/Braintree-Zoning-Fee-Schedule.pdf
- 05 Submit with fees to the Town Office (932 Route 12A) during business hours (Monday-Wednesday 9:00 AM - 4:00 PM) or contact Zoning Administrator Grace Persons at braintreetownclerk2@gmail.com.
- 06 The Zoning Administrator reviews the application. Items requiring Planning Commission or Development Review Board consideration are scheduled for hearings (Planning Commission meets 3rd Thursday).
- 07 Upon approval, permit is issued. Post on property before commencing work.
- 08 Discuss with Zoning Administrator whether a Certificate of Occupancy is required; if so, CO fee is added to the total cost.
Typical processing time: 30 days from receipt of a complete application (Vermont statute requirement)
Required inspections
Scheduling and sequence
- braintreetownclerk2@gmail.com (email)
- 802-728-9787, ext. 105 (phone)
- Inspection hours
- Monday-Wednesday 9:00 AM - 4:00 PM or by appointment
Typical sequence: Planning Commission: 3rd Thursday of each month at the Braintree Town Office. Certificate of Occupancy: Required for some projects; discuss with Zoning Administrator at time of application. DFS inspections for commercial/public buildings: contact DFS at 802-479-7561.
Frequently asked
Common questions about Braintree permits
01 Do I need a building permit in Braintree, VT? ▸
02 How do I apply for a building permit in Braintree, VT? ▸
03 How long does it take to get a building permit in Braintree, VT? ▸
04 What work is exempt from building permits in Braintree, VT? ▸
05 How do I schedule a building inspection in Braintree, VT? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with Town of Braintree Zoning Office before applying. Jaspector is not legal advice.