How to apply for a building permit in Town of Highgate, Vermont. Permit authority, application steps, fees, and inspection requirements.

Last verified
April 2026
On this page 5
§ 01

Permit authority

Zoning Administrator

Street address
2996 VT Route 78, P.O. Box 189, Highgate Center, VT 05459
Coverage
Highgate is a border town with active zoning. Local zoning permits are issued by the Zoning Administrator. Zoning bylaws were updated in 2025 (new Development Regulations effective approximately September 9, 2024). State DFS issues permits for regulated structures.
§ 02

When a permit is required

Permit triggers and exempt work for Highgate

Zoning permits (building permit applications) are required for new construction, additions, alterations, demolition, change of use, and signs per Highgate's Development Regulations (updated 2024).

Standard Vermont exemptions per 24 V.S.A. Sections 4412 and 4413
Normal maintenance and repair not changing use or structure
Agricultural structures on working farms
  • Exempt Standard Vermont exemptions per 24 V.S.A. Sections 4412 and 4413
  • Exempt Normal maintenance and repair not changing use or structure
  • Exempt Agricultural structures on working farms

Note: As specified in Highgate's Development Regulations (2024 edition); verify current bylaws.

Required documents
  • Completed Zoning Permit Application
  • Site plan
  • Building plans
  • Estimated cost
Building code
Highgate Development Regulations (effective approximately September 9, 2024). State 2025 Vermont Fire and Building Safety Code for regulated structures. RBES/CBES apply.
Permit validity
Contact the Zoning Administrator. Standard Vermont practice: 12 months.
Owner-builder
No state general contractor license required; licensed trades required.
Contractor requirements
General contractor -- no Vermont state license required. Electricians and plumbers must be DFS-licensed.

Source: Zoning Administrator ↗

§ 03

Application process

Typical processing: Not publicly specified; up to 30 days per Vermont statute.

  1. 01
    Contact the Zoning Administrator at 802-868-4697 to determine permit requirements.
  2. 02
    Download the Zoning Permit (Building Permit) Application and Fee Schedule from https://www.highgatevt.org/permits-licenses-forms.
  3. 03
    Also download the Development Regulations (Zoning Bylaws) for reference.
  4. 04
    Complete the application with required information, site plan, and building plans.
  5. 05
    Submit application and fees to the Town Office at 2996 VT Route 78, Highgate Center.
  6. 06
    Zoning Administrator reviews for compliance with Highgate's Development Regulations.
  7. 07
    If DRB review is required, applicant is scheduled for a hearing.
  8. 08
    Permit issued upon approval.
  9. 09
    For state-regulated structures (commercial, multifamily, rental), apply to DFS separately.
  10. 10
    Letter of Compliance (Certificate of Compliance) issued upon satisfactory completion at a fee of $50.

Typical processing time: Not publicly specified; up to 30 days per Vermont statute.

Source: Zoning Administrator ↗

§ 04

Required inspections

Scheduling and sequence

How to schedule
  • 802-868-4697 (phone)
Inspection hours
Monday through Thursday, 9:00 AM to 4:00 PM

Typical sequence: Confirm with Zoning Administrator. DFS coordinates for state-permitted projects.

Source: Zoning Administrator ↗

§ 05

Frequently asked

Common questions about Highgate permits

01 Do I need a building permit in Highgate, VT?
Zoning permits (building permit applications) are required for new construction, additions, alterations, demolition, change of use, and signs per Highgate's Development Regulations (updated 2024).
02 How do I apply for a building permit in Highgate, VT?
To apply for a building permit in Highgate, VT, follow these steps: 1. Contact the Zoning Administrator at 802-868-4697 to determine permit requirements. 2. Download the Zoning Permit (Building Permit) Application and Fee Schedule from https://www.highgatevt.org/permits-licenses-forms. 3. Also download the Development Regulations (Zoning Bylaws) for reference. 4. Complete the application with required information, site plan, and building plans. 5. Submit application and fees to the Town Office at 2996 VT Route 78, Highgate Center. 6. Zoning Administrator reviews for compliance with Highgate's Development Regulations. 7. If DRB review is required, applicant is scheduled for a hearing. 8. Permit issued upon approval. 9. For state-regulated structures (commercial, multifamily, rental), apply to DFS separately. 10. Letter of Compliance (Certificate of Compliance) issued upon satisfactory completion at a fee of $50.
03 How long does it take to get a building permit in Highgate, VT?
Building permit processing times in Highgate, VT typically run Not publicly specified; up to 30 days per Vermont statute.. Timelines can vary based on project complexity and current department workload.
04 What work is exempt from building permits in Highgate, VT?
Not all construction work requires a permit in Highgate, VT. The following work is generally exempt: Standard Vermont exemptions per 24 V.S.A. Sections 4412 and 4413; Normal maintenance and repair not changing use or structure; Agricultural structures on working farms. Note: As specified in Highgate's Development Regulations (2024 edition); verify current bylaws. When in doubt, confirm with the local building department before starting work.
05 How do I schedule a building inspection in Highgate, VT?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Highgate, VT via: 802-868-4697.
last verified April 2026 source Zoning Administrator ↗ entry id permits/vermont/franklin/highgate

Educational reference. Permit rules and fees change — confirm current requirements directly with Zoning Administrator before applying. Jaspector is not legal advice.