When a permit is required
Permit triggers and exempt work for Mars Hill
New construction, alterations, additions, demolition, change of use, floodplain development, shoreland zone construction.
- Exempt Ordinary maintenance and repair not affecting structural integrity or life safety
Note: Contact CEO at (207) 554-9051 to confirm exemption for specific projects.
- Land Use Permit Application
- Site plan/sketch
- Building elevations
- Stormwater/erosion controls documentation
- Flood elevation information
- Plumbing/septic permits as applicable
- DEP approvals as required
- Building code
- Local Land Use/Zoning Ordinance governs; MUBEC not mandatory (below 4,000). Confirm current applicable codes with CEO.
- Permit validity
- Contact CEO for current permit term.
- Owner-builder
- Owner-builders may perform work on their own residence; Maine trade licensing rules apply.
- Contractor requirements
- Maine-licensed electricians and plumbers required. No state GC license.
Source: Code Enforcement Office ↗
Application process
Typical processing: CEO review: contact office. Planning Board review requires submission at least 2 weeks before the monthly meeting.
- 01 Contact CEO Bruce Hussey at (207) 554-9051 or the town office at (207) 425-3731 to discuss the project and confirm requirements.
- 02 Obtain the Land Use Permit Application from the Town Office at 37 Main Street or download from the town website.
- 03 Complete the application with: owner/contractor information, tax map/lot, zoning district, project description, square footage, construction cost, lot area, road/water frontage, flood elevation, stormwater/erosion control plan.
- 04 Prepare required attachments: site plan sketch (showing lot lines, setbacks, wells, septic, driveways, areas to be filled/graded) and building sketches/elevations.
- 05 Check with the CEO for any additional required approvals: Planning Board approval, Board of Appeals approval, flood hazard development permit, septic/plumbing permits, DEP permits.
- 06 Submit the completed application and all attachments to the Town Office. Pay applicable fees.
- 07 CEO reviews and may approve, approve with conditions, deny, or forward to the Planning Board. If Planning Board review is required, application must reach the Board through the CEO at least 2 weeks before the next regular meeting (fourth Monday of each month at 7:00 PM).
- 08 Permit is issued upon approval. Post permit on job site; work may not begin until permit is issued.
- 09 Schedule required inspections with the CEO.
Typical processing time: CEO review: contact office. Planning Board review requires submission at least 2 weeks before the monthly meeting.
Source: Code Enforcement Office ↗
Required inspections
Scheduling and sequence
- (207) 554-9051 (phone)
- Inspection hours
- Monday, Tuesday, Thursday 7:30 AM - 5:00 PM; Wednesday 7:30 AM - 6:00 PM; Friday closed
Typical sequence: Contact CEO for current requirements.
Source: Code Enforcement Office ↗
Frequently asked
Common questions about Mars Hill permits
01 Do I need a building permit in Mars Hill, ME? ▸
02 How do I apply for a building permit in Mars Hill, ME? ▸
03 How long does it take to get a building permit in Mars Hill, ME? ▸
04 What work is exempt from building permits in Mars Hill, ME? ▸
05 How do I schedule a building inspection in Mars Hill, ME? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with Code Enforcement Office before applying. Jaspector is not legal advice.