How to apply for a building permit in Town of Houlton, Maine. Permit authority, application steps, fees, and inspection requirements.

Min. permit fee
$30
Last verified
April 2026
On this page 6
§ 01

Permit authority

Code Enforcement Department

Street address
21 Water Street, Houlton, ME 04730
Coverage
Town of Houlton (shire town of Aroostook County). MUBEC enforcement mandatory. Handles building permits, sign permits, shoreland zoning permits, zoning ordinance administration, and complaint investigations. All complaints investigated within 7 days.
Online portal
Building Permit Application
PDF Forms
§ 02

When a permit is required

Permit triggers and exempt work for Houlton

New construction, alterations, additions, demolition, mobile home placement, swimming pools, change of use. Certificate of Occupancy required before occupying any new building or changing building use.

Ordinary maintenance and repair not affecting structural integrity or life safety
  • Exempt Ordinary maintenance and repair not affecting structural integrity or life safety

Note: Contact Code Enforcement at (207) 532-7111 to confirm exemption for specific project types; IBC Section 105.2 and IRC Section R105.2 exemptions apply.

Required documents
  • Completed application
  • Site plan (showing lot shape, dimensions, location, buildings, setbacks)
  • Applicable plans for structural work
Building code
MUBEC; permits issued on or after April 7, 2025 reviewed under 2021 IBC, 2021 IRC, 2021 IEBC, 2021 IECC, 2021 IMC, 2019 ASHRAE 90.1. Prior permits reviewed under 2015 ICC standards.
Permit validity
Permit is invalid if no substantial progress within 6 months; renewal available. Certificate of Occupancy required before occupancy.
Owner-builder
Owner-builders may perform work on their own residence; Maine trade licensing rules apply.
Contractor requirements
Maine-licensed electricians and plumbers required. No state GC license.

Source: Code Enforcement Department ↗

§ 03

Application process

Typical processing: Not formally published; contact office for current turnaround.

  1. 01
    Contact Code Enforcement at (207) 532-7111 or code.enforcement@houlton-maine.com with project details.
  2. 02
    Download the Building Permit application from the town website.
  3. 03
    Complete the application with ownership information, contractor information, and project description.
  4. 04
    Prepare a site plan showing: lot shape, lot dimensions, lot location, buildings to be erected or altered, existing buildings on the lot, adjacent front-yard depths, and any other information required by the Building Inspector or Board of Appeals.
  5. 05
    Submit the application and site plan to Code Enforcement at 21 Water Street. Fees must be paid at submission; starting construction before applying results in double fees.
  6. 06
    Permit is issued upon approval. Post permit on job site.
  7. 07
    If no substantial progress is made within 6 months, the permit becomes invalid unless renewed.
  8. 08
    Schedule required inspections with Code Enforcement.
  9. 09
    Obtain Certificate of Occupancy before occupying the structure; a CO is also required before changing a building's use.

Typical processing time: Not formally published; contact office for current turnaround.

Source: Code Enforcement Department ↗

§ 04

Fee schedule

Houlton building permit fees

Fee type
Amount
01
Minimum permit fee
$30
02
Plan check fee
Included in permit fee
03
Permit fee formula
Projects $0 - $7,000: $30 minimum. Projects over $7,000: Residential $4.00 per $1,000 of project value; Commercial $5.00 per $1,000 of project value.
04
Reinspection fee
Work started before applying triggers double the applicable fee

Pay at Code Enforcement office at time of application submission.

Fees change periodically. Confirm at the official fee schedule ↗ before budgeting.

§ 05

Required inspections

Scheduling and sequence

How to schedule
  • (207) 532-7111 (phone)
  • code.enforcement@houlton-maine.com (email)
Inspection hours
Monday through Friday, 7:30 AM to 4:00 PM

Typical sequence: Typical sequence: Foundation, framing, insulation, rough plumbing, rough electrical, mechanical, final inspection, Certificate of Occupancy.

Source: Code Enforcement Department ↗

§ 06

Frequently asked

Common questions about Houlton permits

01 Do I need a building permit in Houlton, ME?
New construction, alterations, additions, demolition, mobile home placement, swimming pools, change of use. Certificate of Occupancy required before occupying any new building or changing building use.
02 How much does a building permit cost in Houlton, ME?
Building permit fees in Houlton, ME are set by the local building department and vary by project type and valuation. The minimum permit fee is $30. Fees are calculated as: Projects $0 - $7,000: $30 minimum. Projects over $7,000: Residential $4.00 per $1,000 of project value; Commercial $5.00 per $1,000 of project value.. Plan check fee: Included in permit fee.
03 How do I apply for a building permit in Houlton, ME?
To apply for a building permit in Houlton, ME, follow these steps: 1. Contact Code Enforcement at (207) 532-7111 or code.enforcement@houlton-maine.com with project details. 2. Download the Building Permit application from the town website. 3. Complete the application with ownership information, contractor information, and project description. 4. Prepare a site plan showing: lot shape, lot dimensions, lot location, buildings to be erected or altered, existing buildings on the lot, adjacent front-yard depths, and any other information required by the Building Inspector or Board of Appeals. 5. Submit the application and site plan to Code Enforcement at 21 Water Street. Fees must be paid at submission; starting construction before applying results in double fees. 6. Permit is issued upon approval. Post permit on job site. 7. If no substantial progress is made within 6 months, the permit becomes invalid unless renewed. 8. Schedule required inspections with Code Enforcement. 9. Obtain Certificate of Occupancy before occupying the structure; a CO is also required before changing a building's use.
04 How long does it take to get a building permit in Houlton, ME?
Building permit processing times in Houlton, ME typically run Not formally published; contact office for current turnaround.. Timelines can vary based on project complexity and current department workload.
05 What work is exempt from building permits in Houlton, ME?
Not all construction work requires a permit in Houlton, ME. The following work is generally exempt: Ordinary maintenance and repair not affecting structural integrity or life safety. Note: Contact Code Enforcement at (207) 532-7111 to confirm exemption for specific project types; IBC Section 105.2 and IRC Section R105.2 exemptions apply. When in doubt, confirm with the local building department before starting work.
06 How do I schedule a building inspection in Houlton, ME?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Houlton, ME via: (207) 532-7111, code.enforcement@houlton-maine.com.