When a permit is required
Permit triggers and exempt work for Gilmanton
Building permits are required for ALL structures including (but not limited to) dwellings, garages, sheds, decks, and porches. Prior to a permit being granted, all zoning, codes, and regulations must be met.
Note: Not specifically listed in publicly accessible sources. Contact the Community Development Department at (603) 267-6700 for the current list of exempt work. Under NH State Building Code, typical exemptions include ordinary maintenance and repairs that do not affect structural, electrical, plumbing, or mechanical systems.
- Completed application
- Site plan (11x17 inches minimum, to scale, legible) showing structure location and setbacks
- Building plans
- Septic design (if applicable)
- Site engineering (if applicable)
- Building code
- NH State Building Code (RSA 155-A); effective July 1, 2024, the state code uses 2021 IBC/IRC. Gilmanton applies NH State Building Code and references 2021 IRC Table R301.2 for design criteria.
- Contractor requirements
- State-licensed electricians (RSA 319-C) and plumbers (RSA 329-A) required. Residential electrical, mechanical, and plumbing permits are $50 each; solar electric permits are $200.
Application process
Typical processing: 3-5 business days for complete applications
- 01 Contact Community Development staff at the town offices (603-267-6700) with preliminary questions about zoning, setbacks, and whether a permit is required.
- 02 Download or obtain the building permit application packet. All new structures (dwellings, garages, sheds, decks, porches, etc.) require a site plan showing the location of the structure on the lot with setback distances from property boundaries.
- 03 Prepare required documents: completed application; site plan (minimum 11x17 inches, to scale, clearly legible) showing structure location and setbacks; building plans (11x17 inches minimum); septic design (if applicable); site engineering (if applicable).
- 04 The application is received through the Community Development Department, verified by Zoning for compliance with all zoning, codes, and regulations, then processed through the Building Department.
- 05 Completed applications are reviewed within 3-5 business days.
- 06 Upon approval, post permit on site and proceed with construction.
- 07 Schedule inspections with a minimum 48 hours advance notice (call 603-794-8267).
Typical processing time: 3-5 business days for complete applications
Source: Building & Code Enforcement / Community Development Department ↗
Fee schedule
Effective October 1, 2025
Contact town offices for payment instructions.
Fees change periodically. Confirm at the official fee schedule ↗ (effective October 1, 2025) before budgeting.
Required inspections
Scheduling and sequence
- (603) 794-8267 (phone)
- Scheduling deadline
- Minimum 48 hours advance notice
- Inspection hours
- Community Development / Selectmen's Office: Monday-Thursday 8:30 AM-5:00 PM. Building Inspector is part-time; allow at least 48 hours for return calls and inspection scheduling. Same-day inspections are not available.
Frequently asked
Common questions about Gilmanton permits
01 Do I need a building permit in Gilmanton, NH? ▸
02 How much does a building permit cost in Gilmanton, NH? ▸
03 How do I apply for a building permit in Gilmanton, NH? ▸
04 How long does it take to get a building permit in Gilmanton, NH? ▸
05 How do I schedule a building inspection in Gilmanton, NH? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with Building & Code Enforcement / Community Development Department before applying. Jaspector is not legal advice.