How to apply for a building permit in Town of Bolivar, West Virginia. Permit authority, application steps, fees, and inspection requirements.

Last verified
April 2026
On this page 5
§ 01

Permit authority

Town Office, Planning Commission, Zoning Administrator

Street address
Town Office, Bolivar, WV
Coverage
All properties within the Town of Bolivar.
§ 02

When a permit is required

Permit triggers and exempt work for Bolivar

Any extension, construction, sub-construction, enlargement, or removal of any building or structure. Permanent outbuildings/accessory structures (100+ square feet). Carports. Demolition of structures (100+ square feet). Change of use permits.

Structures not exceeding 100 square feet do not require a building permit
  • Exempt Structures not exceeding 100 square feet do not require a building permit

Note: 100-square-foot exemption applies to small sheds and accessory structures. Confirm specific exemptions with Town Office before proceeding.

Required documents
  • Completed permit application
  • Specifications and drawings (to scale)
  • Plot plans
  • Building and floor plans (where applicable)
Building code
2018 International Residential Code (IRC) and 2018 International Building Code (IBC) as of August 1, 2022. Bolivar Part 17 - Building and Housing Ordinance.
Contractor requirements
For residential projects $5,000+: WVCLB license required. For commercial projects $25,000+: WVCLB license required. For electrical work $1,000+: WVCLB license required.

Source: Town Office, Planning Commission, Zoning Administrator ↗

§ 03

Application process

Application → plan check → issuance → inspection → final

  1. 01
    Contact Town Office or visit in person during regular business hours
  2. 02
    Obtain building permit application form
  3. 03
    Complete application with property owner/applicant signature
  4. 04
    Attach specifications and drawings (to scale)
  5. 05
    Attach plot plans
  6. 06
    Attach building and floor plans (where applicable)
  7. 07
    Submit application to Bolivar Planning Commission
  8. 08
    Application must be submitted BEFORE commencement of any construction, enlargement, removal, or use change
  9. 09
    Planning Commission reviews application
  10. 10
    Upon approval, permit issued
  11. 11
    Work may commence upon permit issuance

Source: Town Office, Planning Commission, Zoning Administrator ↗

§ 04

Required inspections

Scheduling and sequence

Inspection hours
Regular business hours (contact Town Office for specific hours)

Typical sequence: Zoning Administrator review of compliance. Code compliance inspection (inspection requirements not specifically detailed). Final inspection upon completion.

Source: Town Office, Planning Commission, Zoning Administrator ↗

§ 05

Frequently asked

Common questions about Bolivar permits

01 Do I need a building permit in Bolivar, WV?
Any extension, construction, sub-construction, enlargement, or removal of any building or structure. Permanent outbuildings/accessory structures (100+ square feet). Carports. Demolition of structures (100+ square feet). Change of use permits.
02 How do I apply for a building permit in Bolivar, WV?
To apply for a building permit in Bolivar, WV, follow these steps: 1. Contact Town Office or visit in person during regular business hours 2. Obtain building permit application form 3. Complete application with property owner/applicant signature 4. Attach specifications and drawings (to scale) 5. Attach plot plans 6. Attach building and floor plans (where applicable) 7. Submit application to Bolivar Planning Commission 8. Application must be submitted BEFORE commencement of any construction, enlargement, removal, or use change 9. Planning Commission reviews application 10. Upon approval, permit issued 11. Work may commence upon permit issuance
03 What work is exempt from building permits in Bolivar, WV?
Not all construction work requires a permit in Bolivar, WV. The following work is generally exempt: Structures not exceeding 100 square feet do not require a building permit. Note: 100-square-foot exemption applies to small sheds and accessory structures. Confirm specific exemptions with Town Office before proceeding. When in doubt, confirm with the local building department before starting work.
last verified April 2026 source Town Office, Planning Commission, Zoning Administrator ↗ entry id permits/west-virginia/jefferson/bolivar

Educational reference. Permit rules and fees change — confirm current requirements directly with Town Office, Planning Commission, Zoning Administrator before applying. Jaspector is not legal advice.