When a permit is required
Permit triggers and exempt work for Oakley
Oakley requires a building permit for construction, enlargement, alteration, repair, movement, improvement, removal, conversion, or demolition of any building or structure.
- Exempt Detached accessory building for storage, playhouse, or similar use not exceeding 200 square feet
- Exempt Fence 6 feet or less in height
- Exempt Retaining wall 4 feet or less in height
- Exempt Water tank supported directly on grade with capacity of 5,000 gallons or less
- Exempt Platform, walk, or driveway not more than 30 inches above grade
- Exempt Painting, papering, and similar finish work
- Exempt Temporary motion picture, television, and theater stage sets and scenery
- Exempt Window awning supported by an exterior wall
- Exempt Prefabricated swimming pool with 5,000 gallon capacity or less
- One set of construction plans including site plan
- One set of structural plans and engineered calculations
- Digital copies of plans
- Dark Sky Compliance Agreement
- South Summit Fire District project clearance form
- Utility inspections, septic permit approval, well documentation, HOA approval, road encroachment permit, and possible engineering studies as applicable
- Building code
- Oakley packet refers applicants to demonstrate compliance with the current Uniform Building Code language, but Utah currently applies the Utah State Construction Code based on the 2021 IBC, 2021 IRC, and 2021 IEBC plus state-adopted companion codes. Oakley may also apply local ordinances such as its Dark Sky ordinance.
- Owner-builder
- No separate owner-builder rule sheet identified.
- Contractor requirements
- Utah state contractor licensing through DOPL applies.
Application process
Application → plan check → issuance → inspection → final
- 01 Review Oakley's Building Permit Application Instructions and gather all required plans, calculations, and outside approvals.
- 02 Submit the building permit application with the $50 application fee and all required documents.
- 03 Oakley reviews the package for completeness and forwards it to the appropriate departments for review.
- 04 Obtain all departmental approvals, including fire and any utility, septic, well, HOA, or encroachment approvals that apply.
- 05 Oakley notifies the applicant when the permit is ready.
- 06 Pay permit fees at issuance; additional engineering review invoices may be billed separately.
- 07 Schedule required inspections with the city and complete final inspection for certificate of occupancy.
Fee schedule
Oakley building permit fees
Application fee is due when the application is submitted; permit fees are due at issuance; engineering review may be billed under separate invoice. Separate impact and connection fees may also apply for city water and sewer.
Fees change periodically. Confirm at the official fee schedule ↗ before budgeting.
Required inspections
Scheduling and sequence
- (435) 783-5734 (phone)
Typical sequence: Oakley publishes a broad list that may include surveyed building envelope or setbacks, temporary power, footing, foundation, sub rough plumbing, shear wall, 4-way, insulation, drywall, shower pan, vapor barrier, lath, power to panel, gas line or meter set, rough, radiant heat tube, bond beam, final, and other project-specific inspections.
Frequently asked
Common questions about Oakley permits
01 Do I need a building permit in Oakley, UT? ▸
02 How much does a building permit cost in Oakley, UT? ▸
03 How do I apply for a building permit in Oakley, UT? ▸
04 What work is exempt from building permits in Oakley, UT? ▸
05 How do I schedule a building inspection in Oakley, UT? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with Oakley City Planning and Land Use before applying. Jaspector is not legal advice.