When a permit is required
Permit triggers and exempt work for Woods Cross
Woods Cross says a building permit is required for all construction within the city except listed exemptions.
- Exempt One-story detached accessory buildings 200 square feet or less that meet zoning requirements.
- Exempt Residential floor coverings.
- Exempt Residential interior wall coverings.
- Exempt Private fencing 6 feet or under that complies with code.
- Exempt Flat cement work.
- Exempt Retaining walls under 4 feet in height.
- Varies by permit
- Commercial checklist specifically requires site plan, electronically stamped plans, supporting documentation, valuation, construction bond agreement, SWPPP, and South Davis Metro Fire approval
- Building code
- Woods Cross posts design criteria showing 2021 IRC, IBC, IMC, IFC, IPC, IFGC, IECC, and IEBC, plus 2020 NEC, all as adopted by the State of Utah.
- Permit validity
- Not clearly posted on the main page.
- Owner-builder
- Not clearly summarized on the page.
- Contractor requirements
- Utah state licensure applies; city commercial materials also require contractors and bonds where applicable.
Application process
Typical processing: New commercial plan review is stated at approximately 21 working days from complete submittal.
- 01 Create a CityInspect account and submit signed application materials through the Woods Cross portal.
- 02 For commercial work, obtain planning approval first where required.
- 03 Upload plans, valuation, site plan, supporting calculations, bond documents, SWPPP, and fire marshal approval as applicable.
- 04 City and consultants review the plans and communicate through the portal.
- 05 Pay any plan review deposit and then final permit fees after approval.
- 06 Permit issues after approvals and fee payment; inspections follow.
Typical processing time: New commercial plan review is stated at approximately 21 working days from complete submittal.
Source: Woods Cross City Building Division / Building Services ↗
Fee schedule
Woods Cross building permit fees
Final permit payments that include impact fees must be made by check; checks may be mailed or paid in person.
Fees change periodically. Confirm at the official fee schedule ↗ before budgeting.
Required inspections
Scheduling and sequence
- Contact Beacon Code Consultants (phone)
- Call, text, or email Beacon Code Consultants (other)
- Inspection hours
- City office hours are Monday through Thursday 7:30 a.m. to 5:30 p.m.
Typical sequence: Depends on permit type; commercial packet contemplates standard office review and field inspections after permit issuance.
Frequently asked
Common questions about Woods Cross permits
01 Do I need a building permit in Woods Cross, UT? ▸
02 How much does a building permit cost in Woods Cross, UT? ▸
03 How do I apply for a building permit in Woods Cross, UT? ▸
04 How long does it take to get a building permit in Woods Cross, UT? ▸
05 What work is exempt from building permits in Woods Cross, UT? ▸
06 How do I schedule a building inspection in Woods Cross, UT? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with Woods Cross City Building Division / Building Services before applying. Jaspector is not legal advice.