When a permit is required
Permit triggers and exempt work for Forest Park
Accessory structures/sheds; additions; all new construction; roofing; siding; decks; fences; garages; gas piping; solar panels; swimming pools; signs; electrical work (IBI permit); plumbing installations (HCHD permit); mechanical equipment.
- Exempt Sheds 100 square feet or less do not require a building permit; however, they must be placed in the required rear yard or buildable area conforming to front and side yard setbacks and the Forest Park Zoning Ordinance.
Note: No additional standalone exempt work list was published on public-facing pages reviewed; confirm specific projects with the Building Department at 513-595-5264.
- Completed permit application
- Three sets of construction documents plus PDF for residential construction
- Site plan based on surveyor boundary survey
- Structural drawings
- Letters of availability from Cincinnati Water Works and Metropolitan Sewer District (single-family homes)
- Building code
- 2019 Ohio Residential Code (residential); Forest Park ordinances FPCO 150, 152, and 154; applicable Ohio Building Code for commercial projects.
- Permit validity
- All exterior work must be completed within six months of permit issuance; permits may be revoked if work halts for six months without a called-for inspection unless an extension is requested in advance.
- Owner-builder
- Not explicitly published on public-facing pages; contact Building Department for guidance.
- Contractor requirements
- State OCILB licenses required for electrical, plumbing, and HVAC trades. Electrical work requires permit from Inspection Bureau, Inc. No Forest Park-specific general contractor registration requirement identified on public-facing pages reviewed; confirm with department.
Application process
Application → plan check → issuance → inspection → final
- 01 Determine permit type and access the appropriate application through the OpenGov portal or the Building Department website.
- 02 Prepare required documents: for residential construction, three complete sets of construction documents plus one PDF version are required, including site plans based on a surveyor boundary survey, floor plans, structural details, and system descriptions.
- 03 Single-family homes need letters of sanitary sewer and water availability from Cincinnati Water Works and Metropolitan Sewer District.
- 04 Submit application online through OpenGov or in person; attach digital drawings as a single PDF when submitting online; digital drawings must be submitted the same day as the application or the application will be voided.
- 05 Pay the minimum processing fee of $295 (non-refundable) at submission; online payment by eCheck or credit card (2.99% surcharge plus $0.99 transaction fee); in-person payment by cash, check, or credit card.
- 06 A confirmation email is sent when the online application is received.
- 07 Obtain separate electrical permit from Inspection Bureau, Inc. (513-381-6080) and plumbing permit from Hamilton County Health Department (513-946-7851) before starting those trades.
- 08 Receive building permit after review; permit is emailed to applicant when processed online.
- 09 Schedule and pass all required inspections; all exterior work must be completed within six months of permit issuance.
- 10 Obtain Certificate of Occupancy upon completion of final inspections.
Fee schedule
Effective 2025
Online payments by eCheck or credit card (2.99% surcharge plus $0.99 transaction fee for credit card); in-person cash, check, or credit card; minimum processing fee is non-refundable.
Fees change periodically. Confirm at the official fee schedule ↗ (effective 2025) before budgeting.
Required inspections
Scheduling and sequence
- Building Department (phone)
- bldgdept@forestpark.org (email)
- Electrical: Inspection Bureau, Inc. (phone)
- Plumbing: Hamilton County Health Department (phone)
- Inspection hours
- Building Department office hours Monday through Friday 8:00 AM to 4:30 PM
Typical sequence: Required inspections per permit type; all exterior work must be completed within six months; final inspection required before Certificate of Occupancy.
Frequently asked
Common questions about Forest Park permits
01 Do I need a building permit in Forest Park, OH? ▸
02 How much does a building permit cost in Forest Park, OH? ▸
03 How do I apply for a building permit in Forest Park, OH? ▸
04 What work is exempt from building permits in Forest Park, OH? ▸
05 How do I schedule a building inspection in Forest Park, OH? ▸