Town of Fletcher, VT - 2026 Building Permit Guide

How to apply for a building permit in Town of Fletcher, Vermont. Permit authority, application steps, fees, and inspection requirements.

Vermont Franklin County Updated March 2026

Permit Authority

Fletcher is a small rural town in southeastern Franklin County. The town has adopted zoning regulations. State DFS issues permits for regulated structures. Note: Fletcher's town office mailing address (Cambridge, VT) is technically in Lamoille County; the town spans the county boundary.

Department
Zoning Administrator
Address
33 Shaw Road, Cambridge, VT 05444
Phone
802-849-6616

Application Process

  1. Contact the Zoning Administrator (Cory Getty) at za@fletchervt.net or the Town Clerk at 802-849-6616 to determine permit requirements.
  2. Obtain the zoning permit application from the Town Office or the Zoning page at https://fletchervt.net/zoning/.
  3. Complete the application with required site plan, building plans, and project description.
  4. Submit completed application with fees at the Town Office or by appointment.
  5. Zoning Administrator reviews for compliance with Fletcher's adopted zoning regulations.
  6. If DRB review is required, applicant is scheduled for a hearing.
  7. Permit issued upon approval.
  8. For state-regulated structures, apply to DFS separately.
  9. Schedule inspections and obtain Certificate of Compliance.

Typical processing time: Not publicly specified; up to 30 days per Vermont statute.

Source: Zoning Administrator

General Requirements

New construction, additions, alterations, demolition, change of use, and signs.

Required Documents

  • Completed application
  • Site plan
  • Building plans
  • Estimated cost
Permit validity
Contact the Zoning Administrator. Standard Vermont practice: 12 months.
Building code
Town of Fletcher zoning regulations (2019 edition). State 2025 Vermont Fire and Building Safety Code for regulated structures. RBES/CBES apply.
Owner-builder
No state general contractor license required; licensed trades required.
Contractor requirements
General contractor -- no Vermont state license required. Electricians and plumbers must be DFS-licensed.

Fees

Payment note
Contact the Zoning Administrator or Town Clerk at 802-849-6616; not publicly posted online. MuniciPay accepted for online payments (2.65% credit/debit fee).

Work That Does NOT Require a Permit

Contact the Zoning Administrator to confirm whether your project requires a permit before starting work.

Inspections

How to Schedule

  • za@fletchervt.net (email)
  • 802-849-6616 (phone)
Inspection hours
Mondays 6:00 PM to 8:00 PM or by appointment with the Zoning Administrator; general office hours Monday through Thursday, 8:00 AM to 3:30 PM

Typical inspection sequence: Confirm with Zoning Administrator. DFS coordinates for state-permitted projects.

Additional Resources

Information on this page was last verified: March 2026. Permit rules and fees change — confirm current requirements directly with the Zoning Administrator before applying.

Frequently Asked Questions

Town of Fletcher Building Permit FAQ

Do I need a building permit in Town of Fletcher, VT?
New construction, additions, alterations, demolition, change of use, and signs.
How do I apply for a building permit in Town of Fletcher, VT?
1. Contact the Zoning Administrator (Cory Getty) at za@fletchervt.net or the Town Clerk at 802-849-6616 to determine permit requirements. 2. Obtain the zoning permit application from the Town Office or the Zoning page at https://fletchervt.net/zoning/. 3. Complete the application with required site plan, building plans, and project description. 4. Submit completed application with fees at the Town Office or by appointment. 5. Zoning Administrator reviews for compliance with Fletcher's adopted zoning regulations. 6. If DRB review is required, applicant is scheduled for a hearing. 7. Permit issued upon approval. 8. For state-regulated structures, apply to DFS separately. 9. Schedule inspections and obtain Certificate of Compliance.
How long does it take to get a building permit in Town of Fletcher, VT?
Typical processing time is Not publicly specified; up to 30 days per Vermont statute..
What work is exempt from building permits in Town of Fletcher, VT?
The following work is generally exempt: Normal maintenance and repair not changing use or structure; Agricultural structures on working farms. Note: Standard Vermont exemptions per 24 V.S.A. Sections 4412 and 4413; verify Fletcher's current zoning regulations for local additions.
How do I schedule a building inspection in Town of Fletcher, VT?
Inspections can be scheduled via: za@fletchervt.net, 802-849-6616.

Need help with your project?

Navigating permits in Town of Fletcher can be complicated.

Jaspector connects you with local experts who can review your scope, verify your contractor, and help you understand what permits your project actually needs.

Learn how Jaspector works
Important: This page is an educational resource provided by jaspector.com. It is not legal advice, and it does not substitute for official guidance from the permit authority listed above. Permit requirements, fees, and processes change frequently. Always verify current requirements directly with the issuing department before beginning any construction project. Use of this page does not create an attorney-client relationship. Jaspector assumes no liability for any outcomes arising from reliance on this information.

Other cities in Franklin County

View all Franklin County jurisdictions →