When a permit is required
Permit triggers and exempt work for Archer City
All persons desiring a building, electrical, plumbing, mechanical, or foundation permit within the city must apply. No placement, construction, remodeling, or refurbishment may begin before permit issuance.
Note: No public exempt-work list was identified. Homeowner registration exemptions do not remove the need for permits.
- Property survey
- Site plan
- Building plan
- Foundation plan
- Lot-plat compliance verification
- Trade licenses as applicable
- Contractor driver license copies
- Proof of insurance as applicable
- Building code
- International Building Code 2021; International Existing Building Code 2021; International Residential Code 2021; International Electrical Code 2020 (NFPA 70); International Fire Code 2021; International Plumbing Code 2021; International Mechanical Code 2021; International Fuel Gas Code 2021; International Energy Conservation Code 2021
- Permit validity
- Permits are valid for 1 year from issuance. Renewal or extension may not exceed 6 months, and the extension fee is one-half of the original permit fee.
- Owner-builder
- A homeowner living in the structure may perform alteration or repair work without contractor registration, but permits and all other code requirements still apply.
- Contractor requirements
- General, plumbing, irrigation, mechanical, and electrical contractors must register with the city and maintain an occupational license.
Application process
Application → plan check → issuance → inspection → final
- 01 Register each contractor with the city and maintain the required occupational license before permit issuance.
- 02 File the permit application with the city secretary.
- 03 Submit one copy each of the property survey, site plan, building plan, and foundation plan, plus any additional copies or supporting items requested by the city secretary or permitting officer.
- 04 Provide proof that the lot complies with city platting requirements and submit trade-license and insurance information as applicable.
- 05 After permitting-officer approval and fee payment, the city secretary issues the permit.
- 06 Obtain required inspections and any certificate of occupancy before use or occupancy.
Source: City Secretary / permitting officer / building inspector ↗
Fee schedule
Archer City building permit fees
Permit fees must be paid before issuance or amendment.
Fees change periodically. Confirm at the official fee schedule ↗ before budgeting.
Required inspections
Scheduling and sequence
- (940) 574-4570 (phone)
Typical sequence: The building inspector has authority over building, plumbing, mechanical, electrical, and foundation inspections. A certificate of occupancy is required before use or occupancy where applicable.
Frequently asked
Common questions about Archer City permits
01 Do I need a building permit in Archer City, TX? ▸
02 How much does a building permit cost in Archer City, TX? ▸
03 How do I apply for a building permit in Archer City, TX? ▸
04 How do I schedule a building inspection in Archer City, TX? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with City Secretary / permitting officer / building inspector before applying. Jaspector is not legal advice.