When a permit is required
Permit triggers and exempt work for Goose Creek
Building permits and inspections are required for covered residential construction and related trades; the city now requires all building permits and plans to be submitted electronically.
Note: No citywide Goose Creek exemption list was published in the public pages reviewed. Contact the Building Inspections Division to confirm whether your project requires a permit.
- Permit application
- Site/plot plan
- Supporting construction documents
- Utility and flood documents where applicable
- Project-specific checklists
- Deck policy documentation if applicable
- Pool requirements documentation if applicable
- Reroofing affidavit if applicable
- Window replacement policy if applicable
- Wind-borne debris affidavit if applicable
- Subcontractor list
- Building code
- 2021 South Carolina code set, 2020 NEC with SC modifications, and related local coastal/wind requirements
- Permit validity
- Thin public data in current Goose Creek pages reviewed.
- Owner-builder
- Owner-builder disclosure states that owners using the exemption may build or improve a one-family or two-family residence for their own use and occupancy, may not build for sale or rent, must supervise construction themselves, and may not hire unlicensed residential builders or specialty contractors.
- Contractor requirements
- Goose Creek requires licensed contractors and specialty contractors under state law; the packet also identifies city business license and permit coordination requirements.
Application process
Typical processing: No standard review time published in current public pages reviewed; an optional express building permit is available for an additional $500 business license fee.
- 01 Create an OpenGov permit portal account and start the applicable application.
- 02 Upload the permit package, including permit application, plans, plot/site plan, and project-specific supporting documents from the residential packet or other city checklists.
- 03 Include specialty items as applicable, such as HVAC Manual J, flood materials, utility letters, and owner-builder disclosure.
- 04 Staff reviews the submittal; corrections are addressed through the portal.
- 05 Pay fees and obtain the issued permit before starting work.
- 06 Schedule required inspections and complete them through to final approval and utility release or certificate issuance.
Typical processing time: No standard review time published in current public pages reviewed; an optional express building permit is available for an additional $500 business license fee.
Source: City of Goose Creek Department of Planning and Zoning and Building Inspection Division ↗
Fee schedule
Goose Creek building permit fees
Residential impact fee is $286.15 per dwelling unit; contractors may buy an express building permit through a $500 additional business license fee.
Fees change periodically. Confirm at the official fee schedule ↗ before budgeting.
Required inspections
Scheduling and sequence
- OpenGov permitting portal (online)
Typical sequence: Project phase inspections are required through completion; utility release follows completion of required inspections and permit conditions.
Source: City of Goose Creek Department of Planning and Zoning and Building Inspection Division ↗
Frequently asked
Common questions about Goose Creek permits
01 Do I need a building permit in Goose Creek, SC? ▸
02 How much does a building permit cost in Goose Creek, SC? ▸
03 How do I apply for a building permit in Goose Creek, SC? ▸
04 How long does it take to get a building permit in Goose Creek, SC? ▸
05 How do I schedule a building inspection in Goose Creek, SC? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with City of Goose Creek Department of Planning and Zoning and Building Inspection Division before applying. Jaspector is not legal advice.