On this page 6
When a permit is required
Permit triggers and exempt work for Fleischmanns
A building permit is required for construction and structural alterations in the Village of Fleischmanns. Permit expires one year from issuance unless renewed or closed by certificate.
Note: Consult the Code Enforcement Officer for current exemptions and clarification on permit requirements.
- Completed building permit application
- Proof of workers' compensation or exemption
- Septic approval (if applicable)
- Plot plan
- Flood-zone permit (if applicable)
- Plan sets
- Building permit fee
- Building code
- New York State Uniform Fire Prevention and Building Code
- Permit validity
- Permit expires one year from issuance unless renewed or closed by certificate of occupancy or compliance.
- Owner-builder
- Owner-builders may apply but must comply with all code requirements.
- Contractor requirements
- Contractors must hold appropriate New York State licenses and carry workers' compensation insurance.
Application process
Typical processing: 1-3 weeks for initial review
- 01 Contact the Code Enforcement Officer (CEO/ZEO) Karl von Hassel at 845-254-4340.
- 02 Request the detailed building permit application and instruction sheet.
- 03 Download or obtain the application from the village website.
- 04 Complete the application with all required project and site information.
- 05 Prepare site plan, construction drawings, and flood-zone permit (if in flood zone).
- 06 Gather required documentation: completed application, fee, workers' compensation documentation or exemption, septic approval (if needed), plot plan, flood-zone permit (if needed), and plan sets.
- 07 Submit all materials to the Code Enforcement Officer.
- 08 Inspections require 72 hours notice to the Code Enforcement Officer.
- 09 No permit will be issued until all listed submission requirements are satisfied.
- 10 Request final inspection and certificate before occupancy.
Typical processing time: 1-3 weeks for initial review
Fee schedule
Effective As published by the Village
Required inspections
Scheduling and sequence
- 845-254-4340 (phone)
- Scheduling deadline
- 72 hours notice to the Code Enforcement Officer required
- Inspection hours
- Contact the Code Enforcement Officer for office hours
- Time windows
- Inspection windows determined by the Code Enforcement Officer
Typical sequence: Occupancy is prohibited without a certificate of occupancy or certificate of compliance.
Contact the Code Enforcement Officer regarding remote inspection availability.
Frequently asked
Common questions about Fleischmanns permits
01 Do I need a building permit in Fleischmanns, NY? ▸
02 How much does a building permit cost in Fleischmanns, NY? ▸
03 How do I apply for a building permit in Fleischmanns, NY? ▸
04 How long does it take to get a building permit in Fleischmanns, NY? ▸
05 How do I schedule a building inspection in Fleischmanns, NY? ▸