When a permit is required
Permit triggers and exempt work for North Bergen Township
A construction permit is required for all new construction, additions, alterations, and repairs within North Bergen Township.
- Exempt Ordinary maintenance (painting, wallpapering, floor covering) without structural or mechanical changes
- Exempt Minor repairs without structural, fire protection, electrical, or plumbing work
- Exempt Temporary structures under 120 sq ft for less than 180 days
- Exempt Fences 6 feet or less in height (except pool barriers)
- Exempt Garden sheds 200 sq ft or less, 10 feet or less in height, with no utility connections
- Exempt Replacement of existing fixtures with equivalent units
- Exempt Repair/replacement of roof covering on detached 1-2 family dwellings
- Exempt Repair/replacement of siding on 1-2 family dwellings
- Exempt Replacement of windows/doors in same opening without structural changes
Note: Even exempt work may require zoning approval. Township Zoning Permit generally required before construction permit. Confirm with Zoning Officer before proceeding.
- Construction Permit Application (F100)
- Applicable Subcode Technical Sections (F110-F150)
- Two sets of plans and specifications
- Site plan with lot lines and setbacks
- Contractor licenses/certificates
- MUA connection fee receipt (if utilities involved)
- Building code
- International Building Code (IBC) with NJ amendments; NJ Uniform Construction Code (UCC)
- Permit validity
- Permit is valid for 12 months from date of last inspection (N.J.A.C. 5:23). Applicant must maintain permit currency through active inspection.
- Owner-builder
- Owner-builders may perform work on own single-family residence with restrictions; state and municipal contractor licensing requirements apply otherwise.
- Contractor requirements
- All contractors must be licensed or registered with NJ Division of Consumer Affairs.
Application process
Typical processing: 20 business days for standard plan review per NJ UCC; 60 business days for projects with asbestos/lead abatement.
- 01 Zoning Review: Contact Zoning Officer to confirm compliance with zoning regulations. Zoning permit generally required before construction permit.
- 02 Complete Application: Gather Construction Permit Application (F100), applicable subcode technical sections (Building, Electrical, Plumbing, Fire), two sets of plans and specifications, site plan with lot lines and setbacks, contractor licenses/certificates.
- 03 MUA Verification: For new construction, obtain North Bergen Municipal Utilities Authority (MUA) connection fee receipt or clearance letter if utilities are involved.
- 04 Submit In Person: Submit complete application package in person to Municipal Building, 4233 Kennedy Boulevard.
- 05 Plan Review: Construction Department reviews for compliance with NJ Uniform Construction Code. Standard review is 20 business days.
- 06 Fee Payment: Pay calculated fees at time of permit issuance.
- 07 Permit Issuance: Permit issued upon approval, fee payment, and MUA clearance if required.
Typical processing time: 20 business days for standard plan review per NJ UCC; 60 business days for projects with asbestos/lead abatement.
Fee schedule
Effective Contact (201) 392-2048 for current fee schedule
Fees collected at time of permit issuance. DCA State surcharge applies to all permits.
Fees change periodically. Confirm at the official fee schedule ↗ (effective Contact (201) 392-2048 for current fee schedule) before budgeting.
Required inspections
Scheduling and sequence
- Construction Department Inspection Request Form (mail)
- (201) 864-0208 (fax)
- (201) 392-2051 (phone)
- Scheduling deadline
- Use Construction Department Inspection Request form. Advance notice required.
- Inspection hours
- Monday-Friday (verify specific hours with office)
- Time windows
- Inspections scheduled based on availability and project scope
Typical sequence: Standard inspections include foundation/footings, framing, rough MEP (mechanical, electrical, plumbing), fire protection, and final inspection. Exact sequence depends on project scope.
In-person inspections required; remote inspections not standard practice.
Frequently asked
Common questions about North Bergen Township permits
01 Do I need a building permit in North Bergen Township, NJ? ▸
02 How much does a building permit cost in North Bergen Township, NJ? ▸
03 How do I apply for a building permit in North Bergen Township, NJ? ▸
04 How long does it take to get a building permit in North Bergen Township, NJ? ▸
05 What work is exempt from building permits in North Bergen Township, NJ? ▸
06 How do I schedule a building inspection in North Bergen Township, NJ? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with Construction Department / Building Department before applying. Jaspector is not legal advice.