When a permit is required
Permit triggers and exempt work for West Deptford Township
A building permit is required for most construction within West Deptford Township.
- Exempt Ordinary Maintenance per N.J.A.C. 5:23-2.7: replacing gutters, painting and trim work, installing/repairing/replacing interior finish in one or two-family dwellings
Note: Township residents reminded to contact Department before beginning work to determine permit requirements. State law mandates fines for work performed without required permits.
- Construction Permit Application (UCC F100)
- Building Subcode Technical Section (UCC F110)
- Electrical Subcode Technical Section (UCC F120)
- Plumbing Subcode Technical Section (UCC F130)
- Fire Subcode Technical Section (UCC F140)
- Mechanical Subcode Technical Section (UCC F145)
- Zoning Permit Application
- Two sets of construction plans
- All prior approvals
- Home Improvement Contractor registration
- Building code
- NJ Uniform Construction Code (UCC)
- Permit validity
- 12 months from date of issuance; extendable upon request. Permit expires if no inspection is requested within 12 months of last inspection.
- Owner-builder
- Owner-builders may prepare own plans for single-family owner-occupied residential projects; building contractors cannot prepare drawings unless licensed as Architect/Engineer.
- Contractor requirements
- Home Improvement Contractor registration required (State law prohibits permits for unregistered contractors who must register). NJ-licensed electricians and plumbers must perform work.
Application process
Typical processing: Up to 30 business days total (10 days zoning + 20 days plan review).
- 01 Obtain Zoning Permit from West Deptford Zoning Officer (Step 1 - up to 10 business days).
- 02 Submit Construction Permit Application with prior approvals (Zoning, Gloucester County Soil Conservation, etc.), two (2) sets of construction plans, and survey for zoning permits.
- 03 Plan review by subcode officials (Step 2 - up to 20 business days).
- 04 Construction Permit issued upon approval (Step 3).
- 05 Pay applicable fees.
Typical processing time: Up to 30 business days total (10 days zoning + 20 days plan review).
Fee schedule
West Deptford Township building permit fees
Minimum fees apply per subcode. Verify current rates with office.
Required inspections
Scheduling and sequence
- (856) 845-4004 (phone)
- Scheduling deadline
- 24 hours required; request by 3:30 PM day before inspection.
- Inspection hours
- Monday-Thursday, 8:30 AM to 4:30 PM. Extended hours: Mondays and Wednesdays until 6:30 PM for plumbing inspections.
Typical sequence: Permit must be posted prominently on site. Approved plans must be kept on site. Non-conforming work requires reinspection; continued non-compliance may result in fines and stop work orders. Applicant must call for final inspections and apply for Certificate of Occupancy.
Frequently asked
Common questions about West Deptford Township permits
01 Do I need a building permit in West Deptford Township, NJ? ▸
02 How much does a building permit cost in West Deptford Township, NJ? ▸
03 How do I apply for a building permit in West Deptford Township, NJ? ▸
04 How long does it take to get a building permit in West Deptford Township, NJ? ▸
05 What work is exempt from building permits in West Deptford Township, NJ? ▸
06 How do I schedule a building inspection in West Deptford Township, NJ? ▸