On this page 6
When a permit is required
Permit triggers and exempt work for Marlow
Any new structure greater than 200 square feet; any modification of an existing structure that changes its height or footprint. A permit is required when erecting or placing a structure for uses outlined in Article IV of the Land Use Regulations, or altering an existing building for such use.
- Exempt Auxiliary buildings (barns and sheds) do not require a permit but must meet regulations set forth in the Land Use Regulations
- Exempt New structures under 200 square feet that do not trigger a change in use per Article IV
- Application with location description
- Nature of work
- Lot plan
- Proposed building location
- Water supply and sewage disposal locations
- Building code
- NH State Building Code; Land Use Regulations and Ordinances available
- Permit validity
- Not confirmed; contact office
- Owner-builder
- Not specified publicly
- Contractor requirements
- NH-licensed electricians and plumbers required
Application process
Typical processing: Not publicly stated
- 01 Download or pick up Building Permit Application from Town Office at 167 NH Route 123 or by contacting John Luke at marlowbuildinginspector@marlownh.gov
- 02 Prepare application with: description of location and nature of proposed building/work; plan showing lot boundaries, proposed building location, other existing structures, water supply and sewage disposal
- 03 Submit completed application to Town Office
- 04 Application reviewed by Building Inspector
- 05 Permit issued upon approval; post on job site
- 06 Schedule inspections with Building Inspector
- 07 Final inspection; Certificate of Occupancy or Certificate of Compliance issued
Typical processing time: Not publicly stated
Source: Building Inspector ↗
Fee schedule
Marlow building permit fees
Contact Building Inspector for current fees
Required inspections
Scheduling and sequence
- (603) 446-2245 Option 2 (phone)
- marlowbuildinginspector@marlownh.gov (email)
- Inspection hours
- Wednesdays and Thursdays 8:00 AM to 6:00 PM (for returning calls, scheduling appointments, and inspections)
Typical sequence: Not detailed publicly; contact Building Inspector
Frequently asked
Common questions about Marlow permits
01 Do I need a building permit in Marlow, NH? ▸
02 How much does a building permit cost in Marlow, NH? ▸
03 How do I apply for a building permit in Marlow, NH? ▸
04 How long does it take to get a building permit in Marlow, NH? ▸
05 What work is exempt from building permits in Marlow, NH? ▸
06 How do I schedule a building inspection in Marlow, NH? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with Building Inspector before applying. Jaspector is not legal advice.