Permit Authority

The Town of Charlestown issues its own local zoning/building permits as a prerequisite to and in coordination with the Cecil County building permit. The Town has a two-tier permit structure (major and minor) and a Historic District Commission. Permits in the Historic District require Historic District Commission review. Major permit applications are reviewed by the Planning and Zoning Commission at monthly meetings. Cecil County is the building authority and performs inspections.

Department
Town of Charlestown (issues local zoning/building permits for town-level work); Cecil County Division of Permits and Inspections (county building permit authority and inspections)
Address
241 Market Street, P.O. Box 154, Charlestown, Maryland 21914
Phone
(410) 287-6173

Online Permit Portal

Platform: OpenGov • Account required: Yes • Submission: Online only

Additional resources:

Application Process

  1. Classify the project as Major or Minor under the Town permit schedule. Major: new dwellings, garages/sheds, additions, swimming pools, decks/patios/porches, rooftop solar, interior renovations, and demolition. Minor: fences, tree removal, major landscaping, relocation/addition of siding, and relocation/addition of windows or doors.
  2. Obtain application from Town Hall at 241 Market Street. Required documents include: completed permit application, scaled site plan showing lot lines, setbacks, structure dimensions, and impervious surface calculations, and building drawings.
  3. Submit application to Town Hall by the Friday before the applicable Planning and Zoning Commission meeting date (for Major permits).
  4. If the project is in the Historic District, submit to the Historic District Commission first before or simultaneously with Planning and Zoning Commission review.
  5. Major permit applicants must obtain county permit and utility fees approval as part of preliminary approval before Town final approval is granted.
  6. Receive Town-issued permit. Pay Town permit fee at time of issuance.
  7. Apply for the Cecil County building permit via OpenGov at cecilcountymd.portal.opengov.com. Include Town permit approval documentation.
  8. Pay county fees; keep permit on site.
  9. Schedule county inspections with 24 hours notice.

Typical processing time: Planning and Zoning Commission meets monthly; work backwards from meeting schedule. Historic District review adds additional time.

Source: Town of Charlestown (issues local zoning/building permits for town-level work); Cecil County Division of Permits and Inspections (county building permit authority and inspections)

General Requirements

No building or structure shall be erected, moved, added to, or structurally altered, or use of land changed without a Town permit in conformance with the Charlestown Zoning Ordinance.

Required Documents

  • Completed permit application
  • Scaled site plan (lot lines, setbacks, structure dimensions, impervious surface calculations)
  • Building drawings
  • County permit and utility fees proof (required for Major permit preliminary approval)
Permit validity
Town zoning/building permits expire one year from date of issue if work has not begun. If work has begun but not been completed, the permit expires two years from issue. Cecil County building permit rules also apply independently.
Building code
Cecil County enforces state-mandated 2021 IBC, 2021 IRC, 2021 IECC, 2021 IPC, 2021 IMC, 2021 IFGC, and 2023 NEC (effective August 2, 2025).
Owner-builder
Property owner may apply. Written authorization required if applicant is not the owner.
Contractor requirements
Same as county-wide -- MHIC for home improvement, Maryland construction license for new/commercial.

Fees

Minimum permit fee
$20.00
Permit fee formula
Town Major permit fee: $50 if obtained before work starts; $250 if obtained after work starts. Town Minor permit fee: $20 if obtained before work starts; $100 if obtained after work starts. County fees: Per Cecil County Development Fee Schedule (updated February 2024); minimum $10.00 non-refundable technology fee at application.
Penalty (no permit)
Failure to obtain permits before construction is a misdemeanor punishable by fines up to $100 or 30 days imprisonment per violation day ($250 for Major permits applied for after work starts; $100 for Minor).

Fees change. Verify current amounts at the official fee schedule.

Work That Does NOT Require a Permit

Contact the Town of Charlestown (issues local zoning/building permits for town-level work); Cecil County Division of Permits and Inspections (county building permit authority and inspections) to confirm whether your project requires a permit before starting work.

Inspections

How to Schedule

  • 410-996-5235 (phone)
Scheduling deadline
24 hours advance notice required.

Typical inspection sequence: All building, plumbing, mechanical, gas, and electrical inspections performed by Cecil County Division of Permits and Inspections or county-approved electrical agencies. Required inspections list provided at permit issuance.

Additional Resources

Information on this page was last verified: March 2026. Permit rules and fees change — confirm current requirements directly with the Town of Charlestown (issues local zoning/building permits for town-level work); Cecil County Division of Permits and Inspections (county building permit authority and inspections) before applying.

Frequently Asked Questions

Town of Charlestown Building Permit FAQ

Do I need a building permit in Town of Charlestown, MD?
No building or structure shall be erected, moved, added to, or structurally altered, or use of land changed without a Town permit in conformance with the Charlestown Zoning Ordinance.
How much does a building permit cost in Town of Charlestown, MD?
The minimum permit fee is $20.00. Fees are calculated as: Town Major permit fee: $50 if obtained before work starts; $250 if obtained after work starts. Town Minor permit fee: $20 if obtained before work starts; $100 if obtained after work starts. County fees: Per Cecil County Development Fee Schedule (updated February 2024); minimum $10.00 non-refundable technology fee at application..
How do I apply for a building permit in Town of Charlestown, MD?
1. Classify the project as Major or Minor under the Town permit schedule. Major: new dwellings, garages/sheds, additions, swimming pools, decks/patios/porches, rooftop solar, interior renovations, and demolition. Minor: fences, tree removal, major landscaping, relocation/addition of siding, and relocation/addition of windows or doors. 2. Obtain application from Town Hall at 241 Market Street. Required documents include: completed permit application, scaled site plan showing lot lines, setbacks, structure dimensions, and impervious surface calculations, and building drawings. 3. Submit application to Town Hall by the Friday before the applicable Planning and Zoning Commission meeting date (for Major permits). 4. If the project is in the Historic District, submit to the Historic District Commission first before or simultaneously with Planning and Zoning Commission review. 5. Major permit applicants must obtain county permit and utility fees approval as part of preliminary approval before Town final approval is granted. 6. Receive Town-issued permit. Pay Town permit fee at time of issuance. 7. Apply for the Cecil County building permit via OpenGov at cecilcountymd.portal.opengov.com. Include Town permit approval documentation. 8. Pay county fees; keep permit on site. 9. Schedule county inspections with 24 hours notice.
How long does it take to get a building permit in Town of Charlestown, MD?
Typical processing time is Planning and Zoning Commission meets monthly; work backwards from meeting schedule. Historic District review adds additional time..
How do I schedule a building inspection in Town of Charlestown, MD?
Inspections can be scheduled via: 410-996-5235. 24 hours advance notice required..

Need help with your project?

Navigating permits in Town of Charlestown can be complicated.

Jaspector connects you with local experts who can review your scope, verify your contractor, and help you understand what permits your project actually needs.

Learn how Jaspector works
Important: This page is an educational resource provided by jaspector.com. It is not legal advice, and it does not substitute for official guidance from the permit authority listed above. Permit requirements, fees, and processes change frequently. Always verify current requirements directly with the issuing department before beginning any construction project. Use of this page does not create an attorney-client relationship. Jaspector assumes no liability for any outcomes arising from reliance on this information.

Other cities in Cecil County

View all Cecil County jurisdictions →