When a permit is required
Permit triggers and exempt work for Caledonia
State-required licensed permits (via B&F): roofing, decks, porches, new construction, additions, sheds, plumbing, electrical, pools with electrical components, detached garages, solar panels. Village-issued permits: fences, chicken coops, window replacements.
- Statement of intent
- Plans/drawings
- Contractor name and proof of insurance
- Project timeline
- Building code
- Under Public Act 103-0510 (effective January 1, 2025), Caledonia must enforce codes at least as stringent as the 2021 IBC, 2021 IRC, 2021 IEBC, NEC 2023, Illinois Energy Conservation Code, Illinois Accessibility Code, and Illinois Plumbing Code. Confirm actual adopted ordinances with the Village Clerk or by downloading the Municipal Code PDF at https://villageofcaledonia.com/ordinances. NOTE: Some codes may have been revised since the original print and may not be current on the website.
- Permit validity
- Permits are valid for 1 year from date of issuance.
- Contractor requirements
- Contractor must provide proof of insurance. IDFPR licenses required for electricians and plumbers. No statewide general contractor license. Confirm any local requirements with the clerk.
Source: Village of Caledonia ↗
Application process
Application → plan check → issuance → inspection → final
- 01 For village-issued permits (fences, chicken coops, window replacements): submit a permit application to the Village Clerk including intent statement, plans, contractor information with proof of insurance, and project timeline.
- 02 Pay applicable fees.
- 03 Permit is valid for 1 year from issuance.
- 04 Inspections must be arranged and conducted before, during, and after project completion. Inspection timing is determined before the permit is issued.
- 05 NOTE: If work begins without a permit, B&F Construction Code Services will issue a Stop Work Order.
Source: Village of Caledonia ↗
Fee schedule
Caledonia building permit fees
Required inspections
Scheduling and sequence
- (847) 428-7010 (phone)
Typical sequence: Inspections required before, during, and after project completion. Specific timing is determined with the applicant before the permit is issued.
Source: Village of Caledonia ↗
Frequently asked
Common questions about Caledonia permits
01 Do I need a building permit in Caledonia, IL? ▸
02 How do I apply for a building permit in Caledonia, IL? ▸
03 How do I schedule a building inspection in Caledonia, IL? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with Village of Caledonia before applying. Jaspector is not legal advice.