jaspector
City building permits

Town of Shalimar

How to apply for a building permit in Town of Shalimar, Florida. Permit authority, application steps, fees, and inspection requirements.

Last verified
April 2026
On this page 6
§ 01

Permit authority

Town of Shalimar

Street address
2 Cherokee Road, Shalimar, FL 32579
Coverage
All properties within the Town of Shalimar. The town uses Okaloosa County for Florida Building Code permitting/inspection functions in many cases. Shalimar requires town permits and contractor tracking certificate.
Additional resources
§ 02

When a permit is required

Permit triggers and exempt work for Shalimar

Except in some minor instances, the town's permit requirements mirror Okaloosa County's requirements and most construction needs a permit.

Only some minor instances are outside the permit requirement; town FAQ does not publish a full exemption chart.
  • Exempt Only some minor instances are outside the permit requirement; town FAQ does not publish a full exemption chart.

Note: Confirm applicable exemptions directly with the town.

Required documents
  • Town building permit application
  • Plans and specifications as applicable
  • Okaloosa County permit documentation where FBC review required
  • Town Contractor Tracking Certificate
Building code
Shalimar's ordinances define a building permit as a town-issued document and define a building official under the current Florida Building Code. Town permit form specifically reminds applicants that work must meet wind-load specifications.
Permit validity
Permits remain valid according to town and state law.
Owner-builder
Town-specific qualification follows Florida law.
Contractor requirements
Contractors working in town limits must contact Town Hall for a Contractor Tracking Certificate. Fee: $30 from October 1 through March 31; $15 from April 1 through September 30.

Source: Town of Shalimar ↗

§ 03

Application process

Typical processing: Contact town for current processing times.

  1. 01
    Submit to the Town of Shalimar first and obtain the required town permit for building, sign, tree removal, and related work.
  2. 02
    Where the work requires Florida Building Code inspection, obtain the related Okaloosa County permit or permit review after town approval.
  3. 03
    Ensure the contractor has a Town of Shalimar Contractor Tracking Certificate or town Business Tax Receipt as required.
  4. 04
    For new construction, provide the town-signed foundation survey and complete town sign-off items before county CO issuance.
  5. 05
    Complete final inspections through the applicable town/county process.

Typical processing time: Contact town for current processing times.

Source: Town of Shalimar ↗

§ 04

Fee schedule

Effective 2026-03

Fee type
Amount
01
Permit fee formula
Contractor Tracking Certificate: $30 (Oct 1-Mar 31) or $15 (Apr 1-Sep 30)

No separate comprehensive building fee table was verified on the town website. Applicants should confirm total fees with the town and Okaloosa County.

§ 05

Required inspections

Scheduling and sequence

How to schedule
Scheduling deadline
Contact town for current scheduling procedures.

Typical sequence: Certified foundation surveys must be approved by the town. The Growth Management Department calls the town on final inspections for new construction so the town can confirm its local requirements before CO issuance.

Source: Town of Shalimar ↗

§ 06

Frequently asked

Common questions about Shalimar permits

01 Do I need a building permit in Shalimar, FL?
Except in some minor instances, the town's permit requirements mirror Okaloosa County's requirements and most construction needs a permit.
02 How much does a building permit cost in Shalimar, FL?
Building permit fees in Shalimar, FL are set by the local building department and vary by project type and valuation. Fees are calculated as: Contractor Tracking Certificate: $30 (Oct 1-Mar 31) or $15 (Apr 1-Sep 30).
03 How do I apply for a building permit in Shalimar, FL?
To apply for a building permit in Shalimar, FL, follow these steps: 1. Submit to the Town of Shalimar first and obtain the required town permit for building, sign, tree removal, and related work. 2. Where the work requires Florida Building Code inspection, obtain the related Okaloosa County permit or permit review after town approval. 3. Ensure the contractor has a Town of Shalimar Contractor Tracking Certificate or town Business Tax Receipt as required. 4. For new construction, provide the town-signed foundation survey and complete town sign-off items before county CO issuance. 5. Complete final inspections through the applicable town/county process.
04 How long does it take to get a building permit in Shalimar, FL?
Building permit processing times in Shalimar, FL typically run Contact town for current processing times.. Timelines can vary based on project complexity and current department workload.
05 What work is exempt from building permits in Shalimar, FL?
Not all construction work requires a permit in Shalimar, FL. The following work is generally exempt: Only some minor instances are outside the permit requirement; town FAQ does not publish a full exemption chart.. Note: Confirm applicable exemptions directly with the town. When in doubt, confirm with the local building department before starting work.
06 How do I schedule a building inspection in Shalimar, FL?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Shalimar, FL via: Town Hall. Contact town for current scheduling procedures..
last verified April 2026 source Town of Shalimar ↗ entry id permits/florida/okaloosa/shalimar

Educational reference. Permit rules and fees change — confirm current requirements directly with Town of Shalimar before applying. Jaspector is not legal advice.