On this page 6
When a permit is required
Permit triggers and exempt work for Mukilteo
A building permit is required for most construction in the City of Mukilteo.
Note: Standard IBC/IRC exemptions apply.
- Completed application
- Plans and specifications
- Submittal checklists (project-type specific)
- Building code
- 2021 International Building Code (IBC) and International Residential Code (IRC) with Washington amendments (effective March 15, 2024).
- Permit validity
- Building permits valid when approved, paid for, and issued.
- Contractor requirements
- All contractors must be registered with Washington State L&I. Electrical permits issued by WA State L&I (Mukilteo does not issue electrical permits).
Source: Permit Center ↗
Application process
Typical processing: 6 weeks for new permits, 4 weeks for resubmittals (typical).
- 01 Create account on Online Permit Portal.
- 02 Submit application with required documents.
- 03 Pay review fees (application not complete until fees paid).
- 04 Plan review (6 weeks for new permits, 4 weeks for resubmittals typical).
- 05 Pay permit fee upon approval.
- 06 Permit issued.
Typical processing time: 6 weeks for new permits, 4 weeks for resubmittals (typical).
Source: Permit Center ↗
Fee schedule
Mukilteo building permit fees
Technology fee: 3% of required permit fees. Administration fee: 15% added when outside costs incurred. Additional fees: State Building Code Council Fee (per state schedule), Extension (one permitted): $150, Completion Permit: 50% of Original Permit Fee, Modification/Revision for Issued Permit: $800.
Required inspections
Scheduling and sequence
- Online Permit Portal or email (online)
- Scheduling deadline
- 3 p.m. the day before for building inspections.
- Time windows
- Monday-Thursday. Most inspections 9:00 a.m. - 3:00 p.m.
Excessive inspection fee: $115 (3+ inspections on same correction).
Source: Permit Center ↗
Frequently asked
Common questions about Mukilteo permits
01 Do I need a building permit in Mukilteo, WA? ▸
02 How much does a building permit cost in Mukilteo, WA? ▸
03 How do I apply for a building permit in Mukilteo, WA? ▸
04 How long does it take to get a building permit in Mukilteo, WA? ▸
05 How do I schedule a building inspection in Mukilteo, WA? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with Permit Center before applying. Jaspector is not legal advice.