How to apply for a building permit in unincorporated Skamania County, Washington. Permit authority, application steps, fees, and inspection requirements.

Last verified
April 2026
On this page 6
§ 01

Permit authority

Skamania County Community Development — Building Division

Street address
Skamania County Courthouse Annex, 170 NW Vancouver Ave, PO Box 1009, Stevenson, WA 98648
Coverage
All unincorporated areas of Skamania County. The county's Building Division also provides contracted building services to the City of Stevenson.
Online portal
Cloudpermit
Cloudpermit
§ 02

When a permit is required

Permit triggers and exempt work for Skamania County

A building permit is required for all new construction, structural remodels, additions, roofing, plumbing, and mechanical work in unincorporated Skamania County. Electrical permits are obtained separately through Washington State L&I; the county does not issue electrical permits or conduct electrical inspections.

One-story detached residential accessory structures used as tool/storage sheds, playhouses, and similar uses, with floor area not exceeding 200 square feet and no plumbing
Fences not over 6 feet in height
Retaining walls not over 4 feet in height (measured from bottom of footing to top of wall), not supporting surcharge or adjacent to a public way
Platforms, decks, sidewalks, and driveways not more than 30 inches above grade and not over a basement or lower story
Painting, papering, tiling, carpeting, cabinets, countertops, and similar finish work
Minor like-for-like repairs not affecting structural elements
  • Exempt One-story detached residential accessory structures used as tool/storage sheds, playhouses, and similar uses, with floor area not exceeding 200 square feet and no plumbing
  • Exempt Fences not over 6 feet in height
  • Exempt Retaining walls not over 4 feet in height (measured from bottom of footing to top of wall), not supporting surcharge or adjacent to a public way
  • Exempt Platforms, decks, sidewalks, and driveways not more than 30 inches above grade and not over a basement or lower story
  • Exempt Painting, papering, tiling, carpeting, cabinets, countertops, and similar finish work
  • Exempt Minor like-for-like repairs not affecting structural elements

Note: An exemption from a building permit does not exempt work from compliance with building codes, zoning setbacks, or other regulations. Exempt work must still comply with all NSA scenic review requirements where applicable and with critical areas regulations (Title 19). Electrical work requires a separate L&I permit regardless of building permit exemption status.

Required documents
  • Site plan (drawn to scale, showing property lines, setbacks, existing structures, and proposed work)
  • Floor plans and elevation drawings
  • Structural plans and specifications
  • Energy code compliance documentation (WSEC)
  • Geotechnical Assessment Report (if in a geologically hazardous area)
  • For NSA properties: NSA approval documentation (obtained separately through Planning Division)
  • Proof of address and parcel number
Building code
2021 International Building Code (IBC) with Washington State amendments (effective March 15, 2024). Also: International Residential Code (IRC), International Mechanical Code (IMC), Uniform Plumbing Code (UPC), International Fire Code (IFC), and Washington State Energy Code (WSEC).
Permit validity
Work must begin within 180 days of permit issuance; first inspection must occur within 180 days. No more than 180 days may elapse between any two consecutive inspections. Failure to maintain inspection activity within these windows may result in permit expiration.
Owner-builder
Permit applications may be submitted by the property owner or by a contractor registered with Washington State L&I.
Contractor requirements
All contractors must be registered with Washington State L&I. Contractor registration is separate from local permit requirements. The county maintains a list of licensed Washington State contractors at https://www.skamaniacounty.org/departments-offices/community-development/building-division/contractors-list.

Source: Skamania County Community Development — Building Division ↗

§ 03

Application process

Typical processing: Completeness determination: 20 calendar days. Plan review and approval timelines vary by project complexity and NSA review requirements (NSA standard review: 7–9 months; expedited for qualifying small-scale projects: 3–4 months).

  1. 01
    Determine land use requirements first. If the parcel is within the Columbia River Gorge National Scenic Area (NSA), an NSA land use review by the Planning Division is typically required before a building permit can issue. NSA review is a separate process from the building permit.
  2. 02
    Check critical areas. If the parcel falls within a Landslide Hazard Area, Erosion Hazard Area, wetland buffer, or other critical area, a Geotechnical Assessment Report prepared by a licensed Washington State engineer may be required before permit approval.
  3. 03
    Register or log into Cloudpermit at https://us.cloudpermit.com/skamaniacounty/login.
  4. 04
    Submit permit application with all required documents (see General Requirements below).
  5. 05
    Receive completeness determination within 20 calendar days of submission. County will notify whether application is complete or requires additional information.
  6. 06
    Plan review by the Building Division proceeds. For NSA projects, copies are sent to the Columbia River Gorge Commission, U.S. Forest Service, Washington Department of Fish and Wildlife, and the Washington Natural Heritage Program.
  7. 07
    Pay fees online through Cloudpermit.
  8. 08
    Permit issued — post permit card at the job site before beginning work.
  9. 09
    Schedule and pass required inspections through Cloudpermit.
  10. 10
    Final inspection and Certificate of Occupancy (CO) — issued upon satisfactory completion of the final inspection for applicable occupancies.

Typical processing time: Completeness determination: 20 calendar days. Plan review and approval timelines vary by project complexity and NSA review requirements (NSA standard review: 7–9 months; expedited for qualifying small-scale projects: 3–4 months).

Source: Skamania County Community Development — Building Division ↗

§ 04

Fee schedule

Skamania County building permit fees

Fee type
Amount
01
Plan check fee
65% of the permit fee
02
Permit fee formula
Permit fee base is determined by construction valuation, calculated as either (a) project square footage multiplied by the per-square-foot construction cost from ICC Building Valuation Data (February 2020 ICC Building Valuation Data baseline), or (b) the fair market value of the improvement — whichever is greater. Plan review fee: 65% of the permit fee, charged in addition to the permit fee.

Fees may be paid online through Cloudpermit by credit card. For a project-specific fee estimate, email building@co.skamania.wa.us with project type and square footage. NSA land use fees: separate fees apply for NSA land use review through the Planning Division. Contact Planning Division at (509) 427-3900 for current NSA application fees.

Fees change periodically. Confirm at the official fee schedule ↗ before budgeting.

§ 05

Required inspections

Scheduling and sequence

How to schedule
Inspection hours
Monday – Thursday, 7:30 AM to 5:30 PM (closed Fridays)

Typical sequence: Typical residential inspection stages: footing/foundation (before concrete placement), framing (before sheathing is installed), rough-in plumbing, rough-in mechanical, insulation, wallboard (if required), energy code compliance, final inspection (all work complete, site accessible). County building staff use Cloudpermit on mobile devices during field inspections; inspection results and correction notices are posted to the permit workspace.

Source: Skamania County Community Development — Building Division ↗

§ 06

Frequently asked

Common questions about unincorporated Skamania County permits

01 Do I need a building permit in unincorporated Skamania County, WA?
A building permit is required for all new construction, structural remodels, additions, roofing, plumbing, and mechanical work in unincorporated Skamania County. Electrical permits are obtained separately through Washington State L&I; the county does not issue electrical permits or conduct electrical inspections.
02 How much does a building permit cost in unincorporated Skamania County, WA?
Building permit fees in unincorporated Skamania County, WA are set by the local building department and vary by project type and valuation. Fees are calculated as: Permit fee base is determined by construction valuation, calculated as either (a) project square footage multiplied by the per-square-foot construction cost from ICC Building Valuation Data (February 2020 ICC Building Valuation Data baseline), or (b) the fair market value of the improvement — whichever is greater. Plan review fee: 65% of the permit fee, charged in addition to the permit fee.. Plan check fee: 65% of the permit fee.
03 How do I apply for a building permit in unincorporated Skamania County, WA?
To apply for a building permit in unincorporated Skamania County, WA, follow these steps: 1. Determine land use requirements first. If the parcel is within the Columbia River Gorge National Scenic Area (NSA), an NSA land use review by the Planning Division is typically required before a building permit can issue. NSA review is a separate process from the building permit. 2. Check critical areas. If the parcel falls within a Landslide Hazard Area, Erosion Hazard Area, wetland buffer, or other critical area, a Geotechnical Assessment Report prepared by a licensed Washington State engineer may be required before permit approval. 3. Register or log into Cloudpermit at https://us.cloudpermit.com/skamaniacounty/login. 4. Submit permit application with all required documents (see General Requirements below). 5. Receive completeness determination within 20 calendar days of submission. County will notify whether application is complete or requires additional information. 6. Plan review by the Building Division proceeds. For NSA projects, copies are sent to the Columbia River Gorge Commission, U.S. Forest Service, Washington Department of Fish and Wildlife, and the Washington Natural Heritage Program. 7. Pay fees online through Cloudpermit. 8. Permit issued — post permit card at the job site before beginning work. 9. Schedule and pass required inspections through Cloudpermit. 10. Final inspection and Certificate of Occupancy (CO) — issued upon satisfactory completion of the final inspection for applicable occupancies.
04 How long does it take to get a building permit in unincorporated Skamania County, WA?
Building permit processing times in unincorporated Skamania County, WA typically run Completeness determination: 20 calendar days. Plan review and approval timelines vary by project complexity and NSA review requirements (NSA standard review: 7–9 months; expedited for qualifying small-scale projects: 3–4 months).. Timelines can vary based on project complexity and current department workload.
05 What work is exempt from building permits in unincorporated Skamania County, WA?
Not all construction work requires a permit in unincorporated Skamania County, WA. The following work is generally exempt: One-story detached residential accessory structures used as tool/storage sheds, playhouses, and similar uses, with floor area not exceeding 200 square feet and no plumbing; Fences not over 6 feet in height; Retaining walls not over 4 feet in height (measured from bottom of footing to top of wall), not supporting surcharge or adjacent to a public way; Platforms, decks, sidewalks, and driveways not more than 30 inches above grade and not over a basement or lower story; Painting, papering, tiling, carpeting, cabinets, countertops, and similar finish work; Minor like-for-like repairs not affecting structural elements. Note: An exemption from a building permit does not exempt work from compliance with building codes, zoning setbacks, or other regulations. Exempt work must still comply with all NSA scenic review requirements where applicable and with critical areas regulations (Title 19). Electrical work requires a separate L&I permit regardless of building permit exemption status. When in doubt, confirm with the local building department before starting work.
06 How do I schedule a building inspection in unincorporated Skamania County, WA?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in unincorporated Skamania County, WA via: Cloudpermit portal, building@co.skamania.wa.us, (509) 427-3925.
last verified April 2026 source Skamania County Community Development — Building Division ↗ entry id permits/washington/skamania/unincorporated

Educational reference. Permit rules and fees change — confirm current requirements directly with Skamania County Community Development — Building Division before applying. Jaspector is not legal advice.