§ 01

Permit authority

Pend Oreille County Community Development Department (per interlocal agreement)

Street address
418 S. Scott Ave., Newport, WA 99156
Coverage
Building permits for properties within the incorporated limits of the Town of Metaline Falls are administered by Pend Oreille County Community Development under an interlocal agreement.
Online portal
Pend Oreille County PublicPortal
PublicPortal
§ 02

When a permit is required

Permit triggers and exempt work for Metaline Falls

Building permits are required for structural work, new construction, manufactured home placement, additions, HVAC installation, and changes of occupancy. A Site Evaluation Application must be completed first.

One-story detached accessory buildings used as tool or storage sheds not exceeding 600 sq. ft. (including attached decks or porches) — exempt as of January 1, 2016, but Site Evaluation Application still required
Private greenhouses
Minor repairs, ordinary maintenance, painting, and cosmetic work per Washington State exemptions (RCW 19.27.040)
  • Exempt One-story detached accessory buildings used as tool or storage sheds not exceeding 600 sq. ft. (including attached decks or porches) — exempt as of January 1, 2016, but Site Evaluation Application still required
  • Exempt Private greenhouses
  • Exempt Minor repairs, ordinary maintenance, painting, and cosmetic work per Washington State exemptions (RCW 19.27.040)

Note: Even exempt work may require a Site Evaluation Application. Confirm project-specific exemptions with the county before proceeding.

Required documents
  • Site Evaluation Application (with scaled sketch of parcel)
  • Building permit application
  • Construction plans and drawings
  • Plot plan
Building code
2021 IBC and 2021 IRC with Washington State amendments (effective March 15, 2024); 2023 BOCC-Approved Building Regulations; 2024 BOCC-Approved Development Regulations (adopted January 27, 2025)
Permit validity
Permits expire one year after issuance and may be renewed up to four times at $55.00 per renewal, for a maximum total duration of five years.
Contractor requirements
Contractors must hold an active Washington State contractor registration with L&I (RCW 18.27).

Source: Pend Oreille County Community Development Department (per interlocal agreement) ↗

§ 03

Application process

Typical processing: Variable; contact the county for current timelines.

  1. 01
    Complete a Site Evaluation Application with Pend Oreille County Community Development before any building or land use development.
  2. 02
    Submit a full permit application with all required documents to the county Community Development Department at 418 S. Scott Ave., Newport.
  3. 03
    Applications will not be reviewed until complete per the checklist.
  4. 04
    Pay permit fees after approval.
  5. 05
    Display permit on the job site.
  6. 06
    Schedule inspections through the county Community Development Department.

Typical processing time: Variable; contact the county for current timelines.

Source: Pend Oreille County Community Development Department (per interlocal agreement) ↗

§ 04

Fee schedule

Metaline Falls building permit fees

Fee type
Amount
01
Permit fee formula
Based on project type and value; contact the county for current fee amounts.

Permit renewal: $55.00 per renewal (up to four renewals maximum).

Fees change periodically. Confirm at the official fee schedule ↗ before budgeting.

§ 05

Required inspections

Scheduling and sequence

How to schedule
  • (509) 447-4821 (phone)
Scheduling deadline
Requests made before 3:00 PM are scheduled for the following business day; requests after 3:00 PM are not scheduled until the second business day. Same-day inspections will not be scheduled.
Inspection hours
Monday–Friday, 8:00 AM–4:30 PM

Typical sequence: Typical stages: foundation, framing/rough-in, insulation, final inspection/Certificate of Occupancy. Inspections for northern Pend Oreille County (including Metaline Falls) are prioritized on Tuesdays and Thursdays. The permit packet must remain on the job site until final inspection is complete.

Source: Pend Oreille County Community Development Department (per interlocal agreement) ↗

§ 06

Frequently asked

Common questions about Metaline Falls permits

01 Do I need a building permit in Metaline Falls, WA?
Building permits are required for structural work, new construction, manufactured home placement, additions, HVAC installation, and changes of occupancy. A Site Evaluation Application must be completed first.
02 How much does a building permit cost in Metaline Falls, WA?
Building permit fees in Metaline Falls, WA are set by the local building department and vary by project type and valuation. Fees are calculated as: Based on project type and value; contact the county for current fee amounts..
03 How do I apply for a building permit in Metaline Falls, WA?
To apply for a building permit in Metaline Falls, WA, follow these steps: 1. Complete a Site Evaluation Application with Pend Oreille County Community Development before any building or land use development. 2. Submit a full permit application with all required documents to the county Community Development Department at 418 S. Scott Ave., Newport. 3. Applications will not be reviewed until complete per the checklist. 4. Pay permit fees after approval. 5. Display permit on the job site. 6. Schedule inspections through the county Community Development Department.
04 How long does it take to get a building permit in Metaline Falls, WA?
Building permit processing times in Metaline Falls, WA typically run Variable; contact the county for current timelines.. Timelines can vary based on project complexity and current department workload.
05 What work is exempt from building permits in Metaline Falls, WA?
Not all construction work requires a permit in Metaline Falls, WA. The following work is generally exempt: One-story detached accessory buildings used as tool or storage sheds not exceeding 600 sq. ft. (including attached decks or porches) — exempt as of January 1, 2016, but Site Evaluation Application still required; Private greenhouses; Minor repairs, ordinary maintenance, painting, and cosmetic work per Washington State exemptions (RCW 19.27.040). Note: Even exempt work may require a Site Evaluation Application. Confirm project-specific exemptions with the county before proceeding. When in doubt, confirm with the local building department before starting work.
06 How do I schedule a building inspection in Metaline Falls, WA?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Metaline Falls, WA via: (509) 447-4821. Requests made before 3:00 PM are scheduled for the following business day; requests after 3:00 PM are not scheduled until the second business day. Same-day inspections will not be scheduled..
last verified April 2026 source Pend Oreille County Community Development Department (per interlocal agreement) ↗ entry id permits/washington/pend-oreille/metaline-falls

Educational reference. Permit rules and fees change — confirm current requirements directly with Pend Oreille County Community Development Department (per interlocal agreement) before applying. Jaspector is not legal advice.

§   Adjacent

Other jurisdictions in Pend Oreille County.

Same county, different permit office. Click for that jurisdiction's full guide.

All Pend Oreille County jurisdictions →