When a permit is required
Permit triggers and exempt work for Metaline Falls
Building permits are required for structural work, new construction, manufactured home placement, additions, HVAC installation, and changes of occupancy. A Site Evaluation Application must be completed first.
- Exempt One-story detached accessory buildings used as tool or storage sheds not exceeding 600 sq. ft. (including attached decks or porches) — exempt as of January 1, 2016, but Site Evaluation Application still required
- Exempt Private greenhouses
- Exempt Minor repairs, ordinary maintenance, painting, and cosmetic work per Washington State exemptions (RCW 19.27.040)
Note: Even exempt work may require a Site Evaluation Application. Confirm project-specific exemptions with the county before proceeding.
- Site Evaluation Application (with scaled sketch of parcel)
- Building permit application
- Construction plans and drawings
- Plot plan
- Building code
- 2021 IBC and 2021 IRC with Washington State amendments (effective March 15, 2024); 2023 BOCC-Approved Building Regulations; 2024 BOCC-Approved Development Regulations (adopted January 27, 2025)
- Permit validity
- Permits expire one year after issuance and may be renewed up to four times at $55.00 per renewal, for a maximum total duration of five years.
- Contractor requirements
- Contractors must hold an active Washington State contractor registration with L&I (RCW 18.27).
Source: Pend Oreille County Community Development Department (per interlocal agreement) ↗
Application process
Typical processing: Variable; contact the county for current timelines.
- 01 Complete a Site Evaluation Application with Pend Oreille County Community Development before any building or land use development.
- 02 Submit a full permit application with all required documents to the county Community Development Department at 418 S. Scott Ave., Newport.
- 03 Applications will not be reviewed until complete per the checklist.
- 04 Pay permit fees after approval.
- 05 Display permit on the job site.
- 06 Schedule inspections through the county Community Development Department.
Typical processing time: Variable; contact the county for current timelines.
Source: Pend Oreille County Community Development Department (per interlocal agreement) ↗
Fee schedule
Metaline Falls building permit fees
Permit renewal: $55.00 per renewal (up to four renewals maximum).
Fees change periodically. Confirm at the official fee schedule ↗ before budgeting.
Required inspections
Scheduling and sequence
- (509) 447-4821 (phone)
- Scheduling deadline
- Requests made before 3:00 PM are scheduled for the following business day; requests after 3:00 PM are not scheduled until the second business day. Same-day inspections will not be scheduled.
- Inspection hours
- Monday–Friday, 8:00 AM–4:30 PM
Typical sequence: Typical stages: foundation, framing/rough-in, insulation, final inspection/Certificate of Occupancy. Inspections for northern Pend Oreille County (including Metaline Falls) are prioritized on Tuesdays and Thursdays. The permit packet must remain on the job site until final inspection is complete.
Source: Pend Oreille County Community Development Department (per interlocal agreement) ↗
Frequently asked
Common questions about Metaline Falls permits
01 Do I need a building permit in Metaline Falls, WA? ▸
02 How much does a building permit cost in Metaline Falls, WA? ▸
03 How do I apply for a building permit in Metaline Falls, WA? ▸
04 How long does it take to get a building permit in Metaline Falls, WA? ▸
05 What work is exempt from building permits in Metaline Falls, WA? ▸
06 How do I schedule a building inspection in Metaline Falls, WA? ▸