On this page 6
When a permit is required
Permit triggers and exempt work for South Cle Elum
Any property owner or authorized representative planning construction, enlargement, alteration, repair, relocation, demolition, or occupancy changes must submit a complete application.
- Exempt Residential accessory structures up to 200 sq ft with no plumbing or mechanical systems, set 10+ feet from other structures and meeting setback requirements
- Exempt Non-residential accessory structures (storage buildings) up to 120 sq ft
- Exempt Fences under 7 feet tall
- Exempt Retaining walls under 4 feet in height (measured from bottom of footing to top of wall)
- Exempt Cosmetic work: painting, wallpaper, flooring, cabinetry (non-structural)
- Exempt Prefabricated pools under 24 inches deep
- Exempt Sidewalks and driveways under 30 inches above grade
- Exempt Playground equipment for single/two-family homes
Note: Exemptions do not authorize work in violation of the building code. All work, including exempt work, must comply with applicable zoning, setback, and critical area requirements.
- Completed General Building Application (signed)
- Vicinity map
- Site plan showing lot lines, setbacks, existing and proposed buildings with dimensions, surface water/wetlands, north arrow, address, access driveways, road name, septic and well locations with setbacks
- Floor plans
- Foundation plans
- Roof framing plans
- Elevations
- Cross sections and construction details
- Plans drawn to minimum 1/4-inch scale on minimum 11" x 17" sheets; two sets required
- Environmental checklist (SEPA) if applicable
- Supplemental information required by County Engineer or Public Works
- Building code
- 2021 I-Codes (IBC, IRC, UPC, IMC, IFC) with Washington State amendments (effective March 15, 2024); International Wildland-Urban Interface Code (IWUIC) as adopted by Kittitas County
- Permit validity
- Not specified; contact Kittitas County CDS for details.
- Contractor requirements
- Washington State contractor registration required. Verify at https://secure.lni.wa.gov/verify/
Source: Community Development Services (Kittitas County CDS) via interlocal agreement ↗
Application process
Typical processing: 2 weeks for Foundation-Only, Fast Track, or Full Review (as of February 2026)
- 01 Complete Water Availability and Preliminary Site Analysis (required before applying).
- 02 Download application forms from Kittitas County CDS at co.kittitas.wa.us/cds/forms.aspx (General Building Application or Foundation-Only Application).
- 03 Prepare construction documents: site plan, floor plans, foundation plans, roof framing plans, elevations, cross sections. Plans must be to minimum 1/4-inch scale on 11" x 17" sheets; two sets required.
- 04 Submit application electronically via Kittitas County CDS upload portal or in-person at 411 N. Ruby St., Suite 2, Ellensburg.
- 05 Plan review conducted (2-week target for Foundation-Only, Fast Track, and Full Review as of February 2026).
- 06 Pay fees and receive permit.
- 07 Schedule inspections through CDS inspection request line.
Typical processing time: 2 weeks for Foundation-Only, Fast Track, or Full Review (as of February 2026)
Source: Community Development Services (Kittitas County CDS) via interlocal agreement ↗
Fee schedule
Effective Current schedule on Kittitas County CDS site
Base fees: permit issuance $150, application/permit extension $70. Use permit fee estimator at co.kittitas.wa.us/cds/building/permit-fee-estimator.aspx for project-specific estimates.
Fees change periodically. Confirm at the official fee schedule ↗ (effective Current schedule on Kittitas County CDS site) before budgeting.
Required inspections
Scheduling and sequence
- (509) 962-7694 — CDS Inspection Request Line (phone)
- cds@co.kittitas.wa.us (email)
- Inspection request form (online)
- Scheduling deadline
- Requests submitted by 2:00 PM typically scheduled the next business day.
- Inspection hours
- Inspections 7:00 AM to 4:00 PM
Typical sequence: Typical stages: form/rebar before concrete pour, hole inspection (pole buildings before backfill), under-floor, exterior shear wall nailing, plumbing rough-in, mechanical rough-in, fire sprinkler (if applicable), framing, insulation, final inspection.
Source: Community Development Services (Kittitas County CDS) via interlocal agreement ↗
Frequently asked
Common questions about South Cle Elum permits
01 Do I need a building permit in South Cle Elum, WA? ▸
02 How much does a building permit cost in South Cle Elum, WA? ▸
03 How do I apply for a building permit in South Cle Elum, WA? ▸
04 How long does it take to get a building permit in South Cle Elum, WA? ▸
05 What work is exempt from building permits in South Cle Elum, WA? ▸