On this page 6
When a permit is required
Permit triggers and exempt work for Bremerton
Building permits required for all construction within the City of Bremerton.
- Exempt One-story detached accessory structures (sheds, playhouses) not exceeding 200 square feet
- Exempt Fences not over 6 feet high
- Exempt Retaining walls not over 4 feet in height (unless supporting surcharge)
- Exempt Water tanks supported directly upon grade (capacity not exceeding 5,000 gallons)
- Exempt Sidewalks and driveways
- Exempt Painting, papering, tiling, carpeting, cabinets, countertops, and similar finish work
- Exempt Prefabricated swimming pools less than 24 inches deep
- Exempt Window awnings not projecting more than 54 inches from exterior wall
- Exempt Decks not more than 30 inches above grade, not attached to dwelling, not serving exit door
- Exempt In-kind window replacement meeting energy code requirements
- Exempt In-kind reroofing (provided roof sheathing is not removed or replaced)
Note: Verify specific exemptions with Bremerton Community Development Department before proceeding. Exempt from building permit does not mean exempt from zoning and other requirements.
- Completed permit application
- Site plan
- Construction plans
- Contractor verification documentation
- Building code
- 2021 Washington State Building Code (amended)
- Permit validity
- Contact department for current validity periods.
- Owner-builder
- Owner-builders must verify ability to perform work within City of Bremerton.
- Contractor requirements
- Contractors must be registered with Washington State L&I (Chapter 18.27 RCW) and provide documentation that contractor is able to perform work within the State of Washington and the City of Bremerton.
Application process
Typical processing: Varies; contact department for current timelines.
- 01 Contact Community Development Department for pre-application guidance.
- 02 Submit complete application with all required documentation.
- 03 Plans reviewed for compliance with adopted codes (2021 Washington State Building Codes effective March 15, 2024).
- 04 Pay applicable fees.
- 05 Permit issued upon approval.
Typical processing time: Varies; contact department for current timelines.
Fee schedule
Bremerton building permit fees
Contact department for payment options and processing fees.
Required inspections
Scheduling and sequence
- (360) 473-5275 (phone)
- Scheduling deadline
- Contact department for current scheduling procedures.
- Inspection hours
- Contact department for current hours.
Typical sequence: Typical sequence includes: Foundation, Framing, Plumbing, Mechanical, and Final inspections. Electrical inspections performed by Washington State L&I (not city).
Frequently asked
Common questions about Bremerton permits
01 Do I need a building permit in Bremerton, WA? ▸
02 How much does a building permit cost in Bremerton, WA? ▸
03 How do I apply for a building permit in Bremerton, WA? ▸
04 How long does it take to get a building permit in Bremerton, WA? ▸
05 What work is exempt from building permits in Bremerton, WA? ▸
06 How do I schedule a building inspection in Bremerton, WA? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with Community Development Department before applying. Jaspector is not legal advice.