How to apply for a building permit in City of Bothell (King County Portion), Washington. Permit authority, application steps, fees, and inspection requirements.

Code adoption
2021 Washington State Building Code
Avg processing
Varies by permit type.
Last verified
April 2026
On this page 5
§ 01

Permit authority

Permit Center (Community Development)

Coverage
All properties within the incorporated City of Bothell (King County portion). Bothell spans King and Snohomish Counties.
Online portal
MyBuildingPermit.com
MyBuildingPermit.com
§ 02

When a permit is required

Permit triggers and exempt work for Bothell (King County Portion)

A building permit is required for most construction within the City of Bothell.

One-story detached accessory structures under 200 sq ft
Fences under 6 feet in height
Decks under 30 inches above grade
Retaining walls under 4 feet
Re-roof overlay
  • Exempt One-story detached accessory structures under 200 sq ft
  • Exempt Fences under 6 feet in height
  • Exempt Decks under 30 inches above grade
  • Exempt Retaining walls under 4 feet
  • Exempt Re-roof overlay

Note: Note: Bothell spans King and Snohomish Counties. Ensure correct jurisdiction selection. Verify exemptions with Permit Center.

Required documents
  • Completed permit application
  • Site plan
  • Construction plans (PDF format)
  • Architectural plans
Building code
2021 Washington State Building Code
Permit validity
Varies by permit type.
Contractor requirements
Contractors must hold a valid Washington State L&I registration.

Source: Permit Center (Community Development) ↗

§ 03

Application process

Typical processing: Varies by permit type.

  1. 01
    Access MyBuildingPermit.com
  2. 02
    Create account
  3. 03
    Select Bothell as jurisdiction (ensure correct jurisdiction selection for King vs Snohomish County)
  4. 04
    Complete online application forms
  5. 05
    Upload PDF plans and documents
  6. 06
    Pay fees online
  7. 07
    City staff reviews application
  8. 08
    Receive electronic permit upon approval

Typical processing time: Varies by permit type.

Source: Permit Center (Community Development) ↗

§ 04

Required inspections

Scheduling and sequence

§ 05

Frequently asked

Common questions about Bothell (King County Portion) permits

01 Do I need a building permit in Bothell (King County Portion), WA?
A building permit is required for most construction within the City of Bothell.
02 How do I apply for a building permit in Bothell (King County Portion), WA?
To apply for a building permit in Bothell (King County Portion), WA, follow these steps: 1. Access MyBuildingPermit.com 2. Create account 3. Select Bothell as jurisdiction (ensure correct jurisdiction selection for King vs Snohomish County) 4. Complete online application forms 5. Upload PDF plans and documents 6. Pay fees online 7. City staff reviews application 8. Receive electronic permit upon approval
03 How long does it take to get a building permit in Bothell (King County Portion), WA?
Building permit processing times in Bothell (King County Portion), WA typically run Varies by permit type.. Timelines can vary based on project complexity and current department workload.
04 What work is exempt from building permits in Bothell (King County Portion), WA?
Not all construction work requires a permit in Bothell (King County Portion), WA. The following work is generally exempt: One-story detached accessory structures under 200 sq ft; Fences under 6 feet in height; Decks under 30 inches above grade; Retaining walls under 4 feet; Re-roof overlay. Note: Note: Bothell spans King and Snohomish Counties. Ensure correct jurisdiction selection. Verify exemptions with Permit Center. When in doubt, confirm with the local building department before starting work.
05 How do I schedule a building inspection in Bothell (King County Portion), WA?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Bothell (King County Portion), WA via: MyBuildingPermit.com.
last verified April 2026 source Permit Center (Community Development) ↗ entry id permits/washington/king/bothell

Educational reference. Permit rules and fees change — confirm current requirements directly with Permit Center (Community Development) before applying. Jaspector is not legal advice.