jaspector
§ WA Clark County
City building permits

City of Battle Ground

How to apply for a building permit in City of Battle Ground, Washington. Permit authority, application steps, fees, and inspection requirements.

Last verified
April 2026
On this page 6
§ 01

Permit authority

City of Battle Ground Community Development Department - Building Division

Street address
City Hall, 109 SW 1st Street, Battle Ground, WA 98604
Coverage
All properties within the incorporated City of Battle Ground.
Online portal
Customer Self-Service (CSS) Portal
CSS Portal
§ 02

When a permit is required

Permit triggers and exempt work for Battle Ground

A building permit is required for all construction work within the City of Battle Ground.

Siding replacement (building permit NOT required; other exemptions follow adopted IBC/IRC codes)
  • Exempt Siding replacement (building permit NOT required; other exemptions follow adopted IBC/IRC codes)

Note: Follow adopted IBC/IRC codes for exemptions.

Required documents
  • Permit application
  • Site plan review (may be required before building permit)
  • All permits must be secured before construction begins
Building code
2021 Washington State Building Code, 2021 Washington State Residential Code, 2021 Washington State Fire Code, 2021 Uniform Plumbing Code, 2021 Washington State Mechanical Code, 2021 Washington State Fuel Gas Code, 2021 Washington State Existing Building Code, 2021 International Property Maintenance Code, 2021 Washington State Energy Code. Design criteria: Frost depth 12 inches minimum; Snow load 25 pounds (live load); Wind speed per IBC 2021 (135 mph ultimate per ASCE 7-16); Seismic Zone D-1; Exposure B.
Contractor requirements
Battle Ground Business License or Endorsement required. Impact and permit fees paid prior to issuance.
§ 03

Application process

Application → plan check → issuance → inspection → final

  1. 01
    Submit permit application through CSS portal.
  2. 02
    Plan review by ICC certified code professionals.
  3. 03
    Permit issuance upon approval and fee payment.
  4. 04
    Schedule inspections through CSS portal (24/7 access).
  5. 05
    Final inspection and Certificate of Occupancy.

Source: City of Battle Ground Community Development Department - Building Division ↗

§ 04

Fee schedule

Battle Ground building permit fees

Fee type
Amount
01
Plan check fee
65% of permit fee
02
Permit fee formula
Based on project valuation
03
Reinspection fee
Additional charges for revisions, re-inspections

Impact fees due prior to Certificate of Occupancy

§ 05

Required inspections

Scheduling and sequence

How to schedule
Scheduling deadline
Must request by midnight for next-day inspection; no phone calls accepted
Inspection hours
Monday-Friday, 8:00 AM - 4:00 PM (excluding holidays)
Time windows
Specific time frames not guaranteed due to volume

Typical sequence: Do not schedule final inspection until electrical is signed off by L&I. Create account and be added to permit to schedule inspections.

§ 06

Frequently asked

Common questions about Battle Ground permits

01 Do I need a building permit in Battle Ground, WA?
A building permit is required for all construction work within the City of Battle Ground.
02 How much does a building permit cost in Battle Ground, WA?
Building permit fees in Battle Ground, WA are set by the local building department and vary by project type and valuation. Fees are calculated as: Based on project valuation. Plan check fee: 65% of permit fee.
03 How do I apply for a building permit in Battle Ground, WA?
To apply for a building permit in Battle Ground, WA, follow these steps: 1. Submit permit application through CSS portal. 2. Plan review by ICC certified code professionals. 3. Permit issuance upon approval and fee payment. 4. Schedule inspections through CSS portal (24/7 access). 5. Final inspection and Certificate of Occupancy.
04 What work is exempt from building permits in Battle Ground, WA?
Not all construction work requires a permit in Battle Ground, WA. The following work is generally exempt: Siding replacement (building permit NOT required; other exemptions follow adopted IBC/IRC codes). Note: Follow adopted IBC/IRC codes for exemptions. When in doubt, confirm with the local building department before starting work.
05 How do I schedule a building inspection in Battle Ground, WA?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Battle Ground, WA via: CSS Portal only. Must request by midnight for next-day inspection; no phone calls accepted.
last verified April 2026 source City of Battle Ground Community Development Department - Building Division ↗ entry id permits/washington/clark/battle-ground

Educational reference. Permit rules and fees change — confirm current requirements directly with City of Battle Ground Community Development Department - Building Division before applying. Jaspector is not legal advice.