When a permit is required
Permit triggers and exempt work for Brigham City
A building permit is required for the construction, addition, alteration, repair, demolition, or change of occupancy of any building or structure within Brigham City, in accordance with the adopted building codes. Permits are also required for mechanical, plumbing, and electrical work beyond minor repairs.
- Exempt Wallpapering, painting, tiling, carpeting, cabinets, countertops, and similar interior finish work
- Exempt Placement of flat concrete work such as a driveway or concrete patio (at grade)
- Exempt Complying agricultural buildings (permit fee is waived, but a permit and inspections are still required)
- Exempt One-story detached accessory structures under 200 sq ft without utilities (statewide IRC baseline; confirm with Brigham City for any local restrictions)
- Exempt Fences not over 7 ft in height
- Exempt Retaining walls not over 4 ft in height not supporting a surcharge
Note: Exempt from building permit does not mean exempt from zoning requirements. Confirm with Brigham City Community and Economic Development before proceeding.
- Completed building permit application
- Site plan (showing property boundaries, existing and proposed structures, setbacks)
- Construction drawings (floor plans, elevations, sections, foundation plan)
- Energy code compliance documentation
- Structural engineering where required
- Any trade-specific applications (electrical, plumbing, mechanical)
- Building code
- Utah State Construction Code: 2021 IBC, 2021 IRC, 2021 IMC, 2021 IPC, 2021 IECC, NEC. Building Chapter 150 of Brigham City Code governs building regulations locally.
- Permit validity
- Applications and issued permits are subject to Utah code-based expiration rules. Confirm current validity period with the Building Division.
- Owner-builder
- Owner-builders must comply with Utah DOPL statewide rules. Brigham City requires applicable disclosure forms.
- Contractor requirements
- All contractors must hold valid Utah DOPL contractor licenses for regulated trade work. A current Brigham City business license may also be required for contractors working in the city.
Source: Brigham City Community and Economic Development Department, Building Division ↗
Application process
Typical processing: Residential: 3-5 business days; Commercial: approximately 5-10 business days. Timing varies by project complexity and submittal completeness.
- 01 Determine the project type (new single-family dwelling, addition/remodel, commercial, etc.) and download the applicable information sheet or application from the Brigham City website.
- 02 Complete the building permit application form. Permit applications are available at City Hall (2nd Floor, 20 N Main St) and online on the city website.
- 03 Prepare required plans and supporting documents per the department's requirements for the project type.
- 04 Submit the application and plans to Brigham City Community and Economic Development, 2nd Floor, 20 N Main Street, or via online submission where available.
- 05 Staff will review for zoning compliance, building code compliance, and other applicable requirements.
- 06 Pay permit fees once the permit is approved. The cost is based on project valuation, calculated using National Building Standards valuation data.
- 07 Receive the issued permit; post on site.
- 08 Schedule all required inspections during construction by calling 435-734-6604 at least 24 hours before the requested inspection time.
Typical processing time: Residential: 3-5 business days; Commercial: approximately 5-10 business days. Timing varies by project complexity and submittal completeness.
Source: Brigham City Community and Economic Development Department, Building Division ↗
Fee schedule
Brigham City building permit fees
Fees change periodically. Verify current amounts directly with Brigham City Community and Economic Development before applying.
Fees change periodically. Confirm at the official fee schedule ↗ before budgeting.
Required inspections
Scheduling and sequence
- 435-734-6604 (phone)
- Scheduling deadline
- At least 24 hours before the requested inspection time
- Inspection hours
- Monday-Friday, 8:00 AM to 5:00 PM
Typical sequence: Typical sequence: Foundation / footing; Rough trades (mechanical, plumbing, electrical) -- framing open; Framing inspection; Insulation inspection; Drywall / sheetrock (if required); Final inspection (all trades, life safety, energy compliance); Certificate of Occupancy
Source: Brigham City Community and Economic Development Department, Building Division ↗
Frequently asked
Common questions about Brigham City permits
01 Do I need a building permit in Brigham City, UT? ▸
02 How much does a building permit cost in Brigham City, UT? ▸
03 How do I apply for a building permit in Brigham City, UT? ▸
04 How long does it take to get a building permit in Brigham City, UT? ▸
05 What work is exempt from building permits in Brigham City, UT? ▸
06 How do I schedule a building inspection in Brigham City, UT? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with Brigham City Community and Economic Development Department, Building Division before applying. Jaspector is not legal advice.