§ 01

Permit authority

Neighborhood & Development Services / Building Development

Street address
1000 N Old Betsy Rd, Cleburne, TX 76031
Coverage
All properties within the incorporated City of Keene.
Online portal
iWorQ
iWorQ
§ 02

When a permit is required

Permit triggers and exempt work for Keene

Building permits cannot be issued until all zoning and platting prerequisites are satisfied. Permits are required for new construction, additions, and alterations.

Note: Confirm permit requirements with Development Services before assuming an exemption.

Required documents
  • Completed permit application
  • Construction plans and specifications
  • Site plan showing property boundaries
  • Proof of zoning compliance
  • Proof of property ownership or authorization
  • Contractor license and registration (if applicable)
Building code
Adopted 2018 International Building, Plumbing, Energy Conservation, Fire, Mechanical, Fuel Gas, and Property Maintenance Codes, 2017 National Electrical Code, 2009 ICC Performance Code, and 2018 NFPA 101 Life Safety Code, with NCTCOG and local amendments.
Owner-builder
Owner-builders may perform work on residential property subject to city requirements.
Contractor requirements
Contractors must hold a valid Texas TDLR license and register with the city.

Source: Neighborhood & Development Services / Building Development ↗

§ 03

Application process

Typical processing: Varies by project complexity; typically 1-2 weeks.

  1. 01
    Review building permit requirements and the residential development packet on the Building Development page.
  2. 02
    Prepare construction plans and site plans meeting city standards; verify zoning and platting compliance.
  3. 03
    Create an account in the iWorQ portal at https://keenetxpermits.portal.iworq.net/portalhome/keenetxpermits
  4. 04
    Submit completed permit application and supporting documents through iWorQ, or email to permits@keenetx.com
  5. 05
    City staff and third-party inspector review application for code compliance.
  6. 06
    Pay applicable permit fees upon approval.
  7. 07
    Obtain permit authorization before construction begins.
  8. 08
    Schedule inspections through iWorQ or by contacting Development Services.

Typical processing time: Varies by project complexity; typically 1-2 weeks.

Source: Neighborhood & Development Services / Building Development ↗

§ 04

Fee schedule

Effective 2026-03

Fee type
Amount
01
Permit fee formula
Contact Development Services for current fee schedule.
§ 05

Required inspections

Scheduling and sequence

How to schedule
  • iWorQ portal (online)
  • 817-641-3336 ext. 130 (phone)
  • permits@keenetx.com (email)
Inspection hours
Standard city business hours.

Typical sequence: Keene uses a third-party inspection company. Required inspections include foundation, framing, MEP rough-in, insulation, drywall, and final building inspections.

Source: Neighborhood & Development Services / Building Development ↗

§ 06

Frequently asked

Common questions about Keene permits

01 Do I need a building permit in Keene, TX?
Building permits cannot be issued until all zoning and platting prerequisites are satisfied. Permits are required for new construction, additions, and alterations.
02 How much does a building permit cost in Keene, TX?
Building permit fees in Keene, TX are set by the local building department and vary by project type and valuation. Fees are calculated as: Contact Development Services for current fee schedule..
03 How do I apply for a building permit in Keene, TX?
To apply for a building permit in Keene, TX, follow these steps: 1. Review building permit requirements and the residential development packet on the Building Development page. 2. Prepare construction plans and site plans meeting city standards; verify zoning and platting compliance. 3. Create an account in the iWorQ portal at https://keenetxpermits.portal.iworq.net/portalhome/keenetxpermits 4. Submit completed permit application and supporting documents through iWorQ, or email to permits@keenetx.com 5. City staff and third-party inspector review application for code compliance. 6. Pay applicable permit fees upon approval. 7. Obtain permit authorization before construction begins. 8. Schedule inspections through iWorQ or by contacting Development Services.
04 How long does it take to get a building permit in Keene, TX?
Building permit processing times in Keene, TX typically run Varies by project complexity; typically 1-2 weeks.. Timelines can vary based on project complexity and current department workload.
05 How do I schedule a building inspection in Keene, TX?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Keene, TX via: iWorQ portal, 817-641-3336 ext. 130, permits@keenetx.com.
last verified April 2026 source Neighborhood & Development Services / Building Development ↗ entry id permits/texas/johnson/keene

Educational reference. Permit rules and fees change — confirm current requirements directly with Neighborhood & Development Services / Building Development before applying. Jaspector is not legal advice.