§ 01

Permit authority

Development Services

Street address
301 E. Jackson Street, Burnet, TX 78611
Coverage
Applies within Burnet city limits. Development Services manages building, planning and zoning, flood hazard mapping, and related permit review.
Online portal
MyGovernmentOnline (MGO)
MyGovernmentOnline
§ 02

When a permit is required

Permit triggers and exempt work for Burnet

Burnet Development Services publishes building permit fees, electrical permit fees, mechanical permit fees, plumbing permit fees, sign permit fees, impact fees, and ICC building code resources, indicating a standard city building permit program for regulated construction work.

Note: No public exempt-work list was found in the sources reviewed.

Required documents
  • Site plan approval or case number
  • Foundation plans
  • Truss information
  • Elevations
  • Floor plans
  • Roof plan
  • Wall sections
  • Electrical plans
  • Plumbing plans
  • Mechanical plans
  • Specifications
  • Utility request items
  • Project-specific documents
Building code
City website publishes ICC Building Codes resources; the exact current edition should be confirmed on the ICC Building Codes page before filing.
Contractor requirements
Trade permits and fee schedules are published for electrical, mechanical, and plumbing work; contractor-specific registration requirements should be confirmed with Development Services.
§ 03

Application process

Typical processing: 2 to 4 weeks for initial comments

  1. 01
    Determine the permit type and gather the required plans and checklists from Development Services.
  2. 02
    Submit the application and all required documents electronically through MyGovernmentOnline.
  3. 03
    Pay the plan review fee when the application is accepted.
  4. 04
    Wait for initial review comments issued through MyGovernmentOnline.
  5. 05
    Revise and resubmit if needed until plans are approved.
  6. 06
    After permit issuance, post the permit and schedule inspections.
  7. 07
    Complete final inspections and any utility or occupancy closeout requirements.

Typical processing time: 2 to 4 weeks for initial comments

Source: Development Services ↗

§ 04

Fee schedule

Burnet building permit fees

Fee type
Amount
01
Minimum permit fee
Residential plan review fee is $100. Commercial plan review total is $200 including building and fire marshal review. Mechanical permit fees start at $10 for certain equipment.
02
Plan check fee
Residential $100. Commercial $100 building review plus $100 fire marshal review.
03
Permit fee formula
Mixed schedule; flat fees for plan review and many trade permits, with other fee pages for building, utility, sign, and impact-related items.
04
Reinspection fee
Mechanical reinspection fee is $35. Other penalty fees depend on the specific permit category.

Portal-based payments are supported through MyGovernmentOnline.

Fees change periodically. Confirm at the official fee schedule ↗ before budgeting.

§ 05

Required inspections

Scheduling and sequence

How to schedule

Typical sequence: Permit packets indicate staged review and inspection after issuance; exact sequences depend on project type and trade scope.

§ 06

Frequently asked

Common questions about Burnet permits

01 Do I need a building permit in Burnet, TX?
Burnet Development Services publishes building permit fees, electrical permit fees, mechanical permit fees, plumbing permit fees, sign permit fees, impact fees, and ICC building code resources, indicating a standard city building permit program for regulated construction work.
02 How much does a building permit cost in Burnet, TX?
Building permit fees in Burnet, TX are set by the local building department and vary by project type and valuation. The minimum permit fee is Residential plan review fee is $100. Commercial plan review total is $200 including building and fire marshal review. Mechanical permit fees start at $10 for certain equipment.. Fees are calculated as: Mixed schedule; flat fees for plan review and many trade permits, with other fee pages for building, utility, sign, and impact-related items.. Plan check fee: Residential $100. Commercial $100 building review plus $100 fire marshal review..
03 How do I apply for a building permit in Burnet, TX?
To apply for a building permit in Burnet, TX, follow these steps: 1. Determine the permit type and gather the required plans and checklists from Development Services. 2. Submit the application and all required documents electronically through MyGovernmentOnline. 3. Pay the plan review fee when the application is accepted. 4. Wait for initial review comments issued through MyGovernmentOnline. 5. Revise and resubmit if needed until plans are approved. 6. After permit issuance, post the permit and schedule inspections. 7. Complete final inspections and any utility or occupancy closeout requirements.
04 How long does it take to get a building permit in Burnet, TX?
Building permit processing times in Burnet, TX typically run 2 to 4 weeks for initial comments. Timelines can vary based on project complexity and current department workload.
05 How do I schedule a building inspection in Burnet, TX?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Burnet, TX via: MyGovernmentOnline.
last verified April 2026 source Development Services ↗ entry id permits/texas/burnet/burnet-city

Educational reference. Permit rules and fees change — confirm current requirements directly with Development Services before applying. Jaspector is not legal advice.