How to apply for a building permit in City of Powers, Oregon. Permit authority, application steps, fees, and inspection requirements.

Avg processing
21 days standard
Last verified
April 2026
On this page 6
§ 01

Permit authority

Coos County Community Development Building Department

Street address
60 E. Second Street, Coquille, OR 97423
Coverage
Powers does not have separate city building authority; all permits issued by Coos County.
Online portal
Oregon ePermitting System
Oregon ePermitting (Accela)
§ 02

When a permit is required

Permit triggers and exempt work for Powers

New construction, manufactured dwellings, alterations, additions, mechanical/electrical/plumbing, demolition

Building code
2023 Oregon Residential Specialty Code (ORSC), 2022 Oregon Structural Specialty Code (OSSC)
Permit validity
180 days; extension required for longer projects
Contractor requirements
Contractors must be licensed through Oregon CCB
§ 03

Application process

Typical processing: 21 days standard

  1. 01
    Submit Building Permit application via Oregon ePermitting or contact Coos County
  2. 02
    Standard Coos County process (21 days typical)
  3. 03
    Contact Coos County office at 60 E. Second Street, Coquille, OR 97423

Typical processing time: 21 days standard

Source: Coos County Community Development Building Department ↗

§ 04

Fee schedule

Powers building permit fees

Fee type
Amount
01
Permit fee formula
Coos County building permit fees

Contact (541) 396-7770 or building@co.coos.or.us for fee schedule.

§ 05

Required inspections

Scheduling and sequence

How to schedule
  • Inspection line: (541) 266-1098 (phone)
  • building@co.coos.or.us (email)
  • Oregon ePermitting system (online)
  • Main office: (541) 396-7770 (phone)

Typical sequence: Coos County Inspectors conduct structural, electrical, plumbing, and mechanical inspections.

Source: Coos County Community Development Building Department ↗

§ 06

Frequently asked

Common questions about Powers permits

01 Do I need a building permit in Powers, OR?
New construction, manufactured dwellings, alterations, additions, mechanical/electrical/plumbing, demolition
02 How much does a building permit cost in Powers, OR?
Building permit fees in Powers, OR are set by the local building department and vary by project type and valuation. Fees are calculated as: Coos County building permit fees.
03 How do I apply for a building permit in Powers, OR?
To apply for a building permit in Powers, OR, follow these steps: 1. Submit Building Permit application via Oregon ePermitting or contact Coos County 2. Standard Coos County process (21 days typical) 3. Contact Coos County office at 60 E. Second Street, Coquille, OR 97423
04 How long does it take to get a building permit in Powers, OR?
Building permit processing times in Powers, OR typically run 21 days standard. Timelines can vary based on project complexity and current department workload.
05 How do I schedule a building inspection in Powers, OR?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Powers, OR via: Inspection line: (541) 266-1098, building@co.coos.or.us, Oregon ePermitting system, Main office: (541) 396-7770.
last verified April 2026 source Coos County Community Development Building Department ↗ entry id permits/oregon/coos/powers

Educational reference. Permit rules and fees change — confirm current requirements directly with Coos County Community Development Building Department before applying. Jaspector is not legal advice.