§ 01

Permit authority

Town of Davidson Planning Department for local permit intake and zoning review; Mecklenburg County Code Enforcement for County building and sign permit review/issuance after Town approval

Street address
Davidson Planning Department, 251 South Street, P.O. Box 579, Davidson, NC 28036; Mecklenburg County LUESA, 2145 Suttle Ave., Charlotte, NC 28208
Coverage
Davidson accepts permit applications through the Town first. For building and sign permits, applicants must then submit the Town-approved permit to Mecklenburg County for County review.
Online portal
Town of Davidson Planning Department Submittal Form
CivicPlus Form Center for Town intake; Mecklenburg County Accela/webpermit for County-side permit completion
§ 02

When a permit is required

Permit triggers and exempt work for Davidson

Davidson uses Town permit forms for building permit categories including new residence, accessory structure, demolition permit, pool, garage, shed, commercial upfit, retaining wall, solar panels, and similar work. Sign permits and temporary use permits are also locally routed through the Town.

Fences do not require a Town permit, but they must still comply with the Davidson Planning Ordinance
  • Exempt Fences do not require a Town permit, but they must still comply with the Davidson Planning Ordinance

Note: Tree removal of trees larger than 12 inches DBH requires a Town permit. Other permit exemptions are not consolidated on the reviewed Town page and should be checked against Davidson ordinance and Mecklenburg County code-permit rules.

Required documents
  • Town permit form
  • Detailed plot/site/sketch plan as applicable
  • Fee payment
  • Permit-type-specific supporting documentation
Building code
Mecklenburg County applies the NC State Building Code for code permit issuance. Davidson regulates local planning and zoning under its Planning Ordinance.
Owner-builder
County homeowner rules apply when the permit proceeds to Mecklenburg County.
Contractor requirements
State contractor-licensing rules apply. Davidson's process does not waive County or state licensing requirements.

Source: Town of Davidson Planning Department for local permit intake and zoning review; Mecklenburg County Code Enforcement for County building and sign permit review/issuance after Town approval ↗

§ 03

Application process

Application → plan check → issuance → inspection → final

  1. 01
    Print the applicable Davidson permit form from the Town list, such as building permit, sign permit, temporary use permit, or home occupation agreement.
  2. 02
    Prepare the required detailed plot, site plan, or sketch plan as applicable.
  3. 03
    Scan the completed permit package and submit it through the Davidson Planning Department Submittal Form, or deliver it by mail or in person to Town Hall.
  4. 04
    Pay the required Town fee at the time of submittal. Davidson states permits are not accepted without payment.
  5. 05
    Wait for Davidson review. The approved permit is sent to the email address supplied in the Town submittal form.
  6. 06
    For building and sign permits, submit the Town-approved permit to Mecklenburg County for County review and issuance.
  7. 07
    Complete County review, fees, and inspections as required.

Source: Town of Davidson Planning Department for local permit intake and zoning review; Mecklenburg County Code Enforcement for County building and sign permit review/issuance after Town approval ↗

§ 04

Fee schedule

Davidson building permit fees

Fee type
Amount
01
Plan check fee
Town fee schedule governs Town planning charges; Mecklenburg County applies separate code review charges after Town approval
02
Permit fee formula
Mixed. Davidson uses Town fee-schedule charges by permit/application type, and County fees apply separately for County review and issuance.
03
Reinspection fee
County reinspection and inspection fees apply where Mecklenburg County performs inspections

Davidson requires fee payment at permit submittal. Building and sign permits then move to Mecklenburg County for additional County fees.

Fees change periodically. Confirm at the official fee schedule ↗ before budgeting.

§ 05

Required inspections

Scheduling and sequence

How to schedule
Inspection hours
Regular municipal business hours

Typical sequence: Town application review and approval, County code review and issuance for building/sign permits, County field inspections, then final approval or CO as applicable

Source: Town of Davidson Planning Department for local permit intake and zoning review; Mecklenburg County Code Enforcement for County building and sign permit review/issuance after Town approval ↗

§ 06

Frequently asked

Common questions about Davidson permits

01 Do I need a building permit in Davidson, NC?
Davidson uses Town permit forms for building permit categories including new residence, accessory structure, demolition permit, pool, garage, shed, commercial upfit, retaining wall, solar panels, and similar work. Sign permits and temporary use permits are also locally routed through the Town.
02 How much does a building permit cost in Davidson, NC?
Building permit fees in Davidson, NC are set by the local building department and vary by project type and valuation. Fees are calculated as: Mixed. Davidson uses Town fee-schedule charges by permit/application type, and County fees apply separately for County review and issuance.. Plan check fee: Town fee schedule governs Town planning charges; Mecklenburg County applies separate code review charges after Town approval.
03 How do I apply for a building permit in Davidson, NC?
To apply for a building permit in Davidson, NC, follow these steps: 1. Print the applicable Davidson permit form from the Town list, such as building permit, sign permit, temporary use permit, or home occupation agreement. 2. Prepare the required detailed plot, site plan, or sketch plan as applicable. 3. Scan the completed permit package and submit it through the Davidson Planning Department Submittal Form, or deliver it by mail or in person to Town Hall. 4. Pay the required Town fee at the time of submittal. Davidson states permits are not accepted without payment. 5. Wait for Davidson review. The approved permit is sent to the email address supplied in the Town submittal form. 6. For building and sign permits, submit the Town-approved permit to Mecklenburg County for County review and issuance. 7. Complete County review, fees, and inspections as required.
04 What work is exempt from building permits in Davidson, NC?
Not all construction work requires a permit in Davidson, NC. The following work is generally exempt: Fences do not require a Town permit, but they must still comply with the Davidson Planning Ordinance. Note: Tree removal of trees larger than 12 inches DBH requires a Town permit. Other permit exemptions are not consolidated on the reviewed Town page and should be checked against Davidson ordinance and Mecklenburg County code-permit rules. When in doubt, confirm with the local building department before starting work.
05 How do I schedule a building inspection in Davidson, NC?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Davidson, NC via: Mecklenburg County Systems.

Educational reference. Permit rules and fees change — confirm current requirements directly with Town of Davidson Planning Department for local permit intake and zoning review; Mecklenburg County Code Enforcement for County building and sign permit review/issuance after Town approval before applying. Jaspector is not legal advice.

§   Adjacent

Other jurisdictions in Mecklenburg County.

Same county, different permit office. Click for that jurisdiction's full guide.

All Mecklenburg County jurisdictions →