When a permit is required
Permit triggers and exempt work for Montour Falls
Building permits are required for construction, enlargement, alteration, and other work under the New York State Uniform Fire Prevention and Building Code.
Note: No separate exempt-work handout identified in village materials. Confirm with Code Enforcement Officer.
- Completed building permit application
- Drawings and plot plan
- Contractor information and insurance documentation
- Energy-code compliance documents for certain projects
- Stamped plans from NY licensed engineer or architect for larger projects
- Building code
- New York State Uniform Fire Prevention and Building Code and Village of Montour Falls code
- Permit validity
- Permit is valid for one year. Work must commence within six months of issuance.
- Owner-builder
- Owner-builders may file directly.
- Contractor requirements
- Contractors must hold valid New York State licenses and insurance.
Application process
Typical processing: Variable; generally 1-4 weeks depending on application completeness. Incomplete applications delay permit issuance.
- 01 Download or obtain the village's 2025 building permit application.
- 02 Complete the application with property, owner, and work-scope information.
- 03 Prepare drawings, plot plan, contractor information, and insurance documentation as required by the packet.
- 04 For new structures, major additions, and major renovations, provide energy-code compliance documents and, if applicable, New York licensed engineer or architect stamped plans.
- 05 Submit completed application and supporting materials to the Code Enforcement Office.
- 06 Pay permit fees.
- 07 Schedule inspections with the Code Enforcement Office before work is covered.
Typical processing time: Variable; generally 1-4 weeks depending on application completeness. Incomplete applications delay permit issuance.
Fee schedule
Montour Falls building permit fees
Payment due upon permit issuance. Confirm payment method with Code Enforcement Office.
Fees change periodically. Confirm at the official fee schedule ↗ before budgeting.
Required inspections
Scheduling and sequence
- (607) 738-4323 (phone)
- Scheduling deadline
- Contact Code Enforcement Office at least 48 hours before desired inspection.
- Inspection hours
- Posted office hours
Typical sequence: Permit work must be visually inspected by the Code Enforcement Office and comply with the village code and New York code. Occupancy requiring a certificate cannot begin before issuance.
Frequently asked
Common questions about Montour Falls permits
01 Do I need a building permit in Montour Falls, NY? ▸
02 How much does a building permit cost in Montour Falls, NY? ▸
03 How do I apply for a building permit in Montour Falls, NY? ▸
04 How long does it take to get a building permit in Montour Falls, NY? ▸
05 How do I schedule a building inspection in Montour Falls, NY? ▸