When a permit is required
Permit triggers and exempt work for Ellicottville
The village publishes active building permit forms and requires permits for work subject to the Uniform Code.
Note: Verify exemptions with Village Building Department
- Building permit application
- Zoning permit application
- Signed drawing sets (stamped by design professional for structures over 1,500 sq ft)
- Building code
- New York Uniform Fire Prevention and Building Code
- Permit validity
- Varies per village guidelines
- Owner-builder
- It is unlawful to occupy a building or structure for which a permit was required without first obtaining a certificate of occupancy.
- Contractor requirements
- Contractors must comply with village licensing and code requirements.
Application process
Typical processing: Varies
- 01 Download or request the village building permit application and checklist.
- 02 Prepare signed drawing sets and supporting documents.
- 03 Submit completed application with all required attachments.
- 04 Pay applicable permit fees.
- 05 Receive permit approval.
- 06 Schedule inspections and obtain certificate of occupancy when required.
Typical processing time: Varies
Source: Building Department ↗
Required inspections
Scheduling and sequence
- Village Building Department (phone)
- Scheduling deadline
- Notify Code Enforcement Officer 48 hours before inspections are needed.
Typical sequence: Applicant responsible for scheduling and coordinating with Code Enforcement Officer
Frequently asked
Common questions about Ellicottville permits
01 Do I need a building permit in Ellicottville, NY? ▸
02 How do I apply for a building permit in Ellicottville, NY? ▸
03 How long does it take to get a building permit in Ellicottville, NY? ▸
04 How do I schedule a building inspection in Ellicottville, NY? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with Building Department before applying. Jaspector is not legal advice.