When a permit is required
Permit triggers and exempt work for Aztec
New construction, additions, structural alterations, demolitions, re-roofs, solar installations, and accessory structures over 120 sq ft. Electrical, plumbing, and mechanical permits for installation or significant repair.
- Completed permit application
- Site plan to scale showing property lines, setbacks, and structure footprint
- Construction drawings (scaled, showing floor plans, elevations, sections)
- Energy compliance documentation (NM-adopted IECC)
- Contractor license number (NM CID GB-2 or GB-98)
- Homeowner permit affidavit (if owner-builder)
- Liquid Waste Disposal Permit (NM ENV) if on septic
- Building code
- State-mandated codes: 2021 IRC/IBC, 2020 NEC, 2021 IMC, 2021 IPC, 2021 IECC, all with NM amendments
- Permit validity
- Standard 180-day commencement and 180-day suspension rules per NM CID standards. Verify current city policy at (505) 334-7671.
- Owner-builder
- Allowed per 14.5.2.18 NMAC for primary residence; one permit per 12 months; must occupy as primary residence.
- Contractor requirements
- Valid NM CID license required. GB-2 residential, GB-98 general commercial. Trade licenses for electrical, plumbing, mechanical. Verify at: https://www.rld.nm.gov/construction-industries/
Application process
Typical processing: Residential permits typically within 5-10 business days. Call (505) 334-7671 for current workload estimates.
- 01 Verify the property is within Aztec city limits. Use city maps or contact (505) 334-7671.
- 02 Determine permit type(s) required: building, electrical, plumbing, mechanical.
- 03 Prepare required documents: site plan, construction drawings, contractor info or homeowner affidavit, energy compliance documentation.
- 04 Submit application in person at 201 W. Chaco Street, Aztec. Call (505) 334-7671 in advance to confirm required documents and current procedures.
- 05 Pay plan review fee at submittal.
- 06 Await plan review and respond to any correction requests.
- 07 Upon approval, pay remaining permit fee and receive issued permit.
- 08 Post permit on job site; begin construction.
- 09 Schedule required inspections through Building Services at each milestone.
- 10 Final inspection; Certificate of Occupancy issued.
Typical processing time: Residential permits typically within 5-10 business days. Call (505) 334-7671 for current workload estimates.
Source: City of Aztec -- Building Services (within the Planning and Community Development Department) ↗
Fee schedule
Aztec building permit fees
In-person at 201 W. Chaco Street.
Required inspections
Scheduling and sequence
- (505) 334-7671 (phone)
- Scheduling deadline
- At least one business day advance notice recommended.
- Inspection hours
- Monday through Friday, normal business hours
Typical sequence: Typical sequence for residential construction: 1) Foundation/footing inspection (before concrete pour); 2) Underground utilities inspection (under-slab plumbing and electrical, before pour); 3) Framing inspection (rough framing and bracing complete, before insulation); 4) Rough mechanical, electrical, and plumbing inspections; 5) Insulation inspection; 6) Final inspection; 7) Certificate of Occupancy.
Source: City of Aztec -- Building Services (within the Planning and Community Development Department) ↗
Frequently asked
Common questions about Aztec permits
01 Do I need a building permit in Aztec, NM? ▸
02 How much does a building permit cost in Aztec, NM? ▸
03 How do I apply for a building permit in Aztec, NM? ▸
04 How long does it take to get a building permit in Aztec, NM? ▸
05 How do I schedule a building inspection in Aztec, NM? ▸