§ 01

Permit authority

Construction Department

Street address
1 Municipal Plaza, Bloomfield, NJ 07003
Coverage
All properties within the Township of Bloomfield.
§ 02

When a permit is required

Permit triggers and exempt work for Bloomfield

Zoning permit and construction permit required for new construction, additions, enclosing porches, finishing basements/attics, decks, pools, fences, retaining walls, driveways, walkways, patios, generators, HVAC, sheds, and commercial change of use.

Routine maintenance including roofing, siding, and window/door replacement (as long as no structural change)
Small repairs that do not structurally change the building
  • Exempt Routine maintenance including roofing, siding, and window/door replacement (as long as no structural change)
  • Exempt Small repairs that do not structurally change the building

Note: Confirm exemption status with the Construction Department before proceeding.

Required documents
  • Zoning permit application with current property survey
  • Construction Permit Application (NJ DCA Form F100) with subcode sections
  • Plans/specifications (2 sets residential, 3 sets commercial)
  • Commercial plans must be sealed by NJ-licensed professional
  • Contractor credentials and insurance verification
Building code
NJ Uniform Construction Code (UCC) based on International Building Code (IBC) with NJ-specific amendments
Permit validity
NJ UCC permits valid for 12 months from last inspection; work must begin within 12 months of permit issuance.
Contractor requirements
All contractors must hold valid NJ registrations and licenses. Commercial plans require NJ-licensed professional seal.

Source: Construction Department ↗

§ 03

Application process

Typical processing: Zoning permit: 10 business days; Construction permit: 20 business days under NJ UCC for complete applications.

  1. 01
    Apply for zoning permit before construction permit (10 business day review period).
  2. 02
    Submit current property survey with zoning application.
  3. 03
    Submit Construction Permit Application with applicable subcode sections.
  4. 04
    Provide plans: 2 sets for residential, 3 sets for commercial.
  5. 05
    Commercial plans must be signed and sealed by NJ-licensed professional.
  6. 06
    Pay fees including plan review fees.
  7. 07
    Post permit placard visibly from street.

Typical processing time: Zoning permit: 10 business days; Construction permit: 20 business days under NJ UCC for complete applications.

Source: Construction Department ↗

§ 04

Fee schedule

Effective May 19, 2025

Fee type
Amount
01
Plan check fee
Typically 20% of permit fee due at submission
02
Permit fee formula
Construction Fee Ordinance dated 5/19/25 applies.

Contact Construction Department for specific fee schedule. Plan review fees typically 20% of permit fee due at submission.

§ 05

Required inspections

Scheduling and sequence

How to schedule
  • (973) 680-4053 (phone)

Typical sequence: Required inspections at various construction phases. Approved plans must be kept on site at all times. Inspector will not conduct inspection without plans on site. Final inspection and Certificate of Occupancy required.

Source: Construction Department ↗

§ 06

Frequently asked

Common questions about Bloomfield permits

01 Do I need a building permit in Bloomfield, NJ?
Zoning permit and construction permit required for new construction, additions, enclosing porches, finishing basements/attics, decks, pools, fences, retaining walls, driveways, walkways, patios, generators, HVAC, sheds, and commercial change of use.
02 How much does a building permit cost in Bloomfield, NJ?
Building permit fees in Bloomfield, NJ are set by the local building department and vary by project type and valuation. Fees are calculated as: Construction Fee Ordinance dated 5/19/25 applies.. Plan check fee: Typically 20% of permit fee due at submission.
03 How do I apply for a building permit in Bloomfield, NJ?
To apply for a building permit in Bloomfield, NJ, follow these steps: 1. Apply for zoning permit before construction permit (10 business day review period). 2. Submit current property survey with zoning application. 3. Submit Construction Permit Application with applicable subcode sections. 4. Provide plans: 2 sets for residential, 3 sets for commercial. 5. Commercial plans must be signed and sealed by NJ-licensed professional. 6. Pay fees including plan review fees. 7. Post permit placard visibly from street.
04 How long does it take to get a building permit in Bloomfield, NJ?
Building permit processing times in Bloomfield, NJ typically run Zoning permit: 10 business days; Construction permit: 20 business days under NJ UCC for complete applications.. Timelines can vary based on project complexity and current department workload.
05 What work is exempt from building permits in Bloomfield, NJ?
Not all construction work requires a permit in Bloomfield, NJ. The following work is generally exempt: Routine maintenance including roofing, siding, and window/door replacement (as long as no structural change); Small repairs that do not structurally change the building. Note: Confirm exemption status with the Construction Department before proceeding. When in doubt, confirm with the local building department before starting work.
06 How do I schedule a building inspection in Bloomfield, NJ?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Bloomfield, NJ via: (973) 680-4053.
last verified April 2026 source Construction Department ↗ entry id permits/new-jersey/essex/bloomfield-township

Educational reference. Permit rules and fees change — confirm current requirements directly with Construction Department before applying. Jaspector is not legal advice.