§ 01

Permit authority

Department of Licensing and Inspection

Street address
Burlington Township Municipal Building, 851 Old York Road, Burlington, NJ 08016
Coverage
All properties within Burlington Township.
§ 02

When a permit is required

Permit triggers and exempt work for Burlington Township

A construction permit is required for most work as per NJ Uniform Construction Code (UCC).

Ordinary repairs not involving code violations
Minor work as determined by subcode official and Construction Code Official
Emergency work (permit required within 72 hours)
Cosmetic repairs
Non-structural maintenance
  • Exempt Ordinary repairs not involving code violations
  • Exempt Minor work as determined by subcode official and Construction Code Official
  • Exempt Emergency work (permit required within 72 hours)
  • Exempt Cosmetic repairs
  • Exempt Non-structural maintenance

Note: Zoning approval may be required before construction permit issuance. All taxes and assessments must be current. Site plan approval may be required for certain projects.

Required documents
  • UCC-F100 Construction Permit Application
  • Applicable subcode technical sections
  • Three sets of construction plans
  • Property survey or site plan
  • Contractor proof of insurance and NJ licenses
  • Home Improvement Contractor registration (residential)
Building code
NJ Uniform Construction Code (UCC)
Permit validity
12 months from most recent inspection.
Owner-builder
Owner-builders must comply with NJ UCC requirements and contractor licensing where applicable.
Contractor requirements
Contractors must hold valid NJ licenses, insurance, and be registered as Home Improvement Contractors for residential work.
§ 03

Application process

Typical processing: Varies by project complexity; typically 2-4 weeks for plan review.

  1. 01
    Visit Department of Licensing and Inspection to obtain application packet.
  2. 02
    Complete NJ DCA UCC-F100 Construction Permit Application.
  3. 03
    Submit three sets of plans for plan review.
  4. 04
    Include site plan, construction drawings, specifications.
  5. 05
    Provide contractor licenses and insurance certificates.
  6. 06
    Pay plan review fee before review begins (25% of construction permit fee).
  7. 07
    Submit documents in-person at Municipal Building.
  8. 08
    Respond to plan review comments if required.
  9. 09
    Pay remaining permit fees upon approval.
  10. 10
    Obtain final permit and post on site before construction begins.

Typical processing time: Varies by project complexity; typically 2-4 weeks for plan review.

§ 04

Fee schedule

Burlington Township building permit fees

Fee type
Amount
01
Minimum permit fee
$70
02
Plan check fee
25% of construction permit fee
03
Permit fee formula
New Structures/Additions: $0.025 per cubic foot of building volume; Construction Trailer: $100 flat fee; Tent (under 900 sq ft): $70; Tent (over 900 sq ft or over 30 ft): $100; Roofing/Siding (Residential): $70 flat fee; Plumbing/Mechanical Fixtures: $25 per item (sinks, toilets, tubs, water heaters, dishwashers, vents, hose bibs, etc.).

State Training Surcharge: $0.00371 per cubic foot (new construction) or $1.90 per $1,000 of value ($1 minimum). Plan review amount credited toward construction permit fee.

§ 05

Required inspections

Scheduling and sequence

How to schedule
  • (609) 239-6412 (phone)
  • Department of Licensing and Inspection (in-person)
Scheduling deadline
Contact Department of Licensing and Inspection.
Inspection hours
Monday-Friday (contact for specific hours).

Typical sequence: Standard inspections: Footings (before concrete), Foundation/walls to grade (before backfill), Utility services, Rough inspections (all subcodes), Framing inspection, Insulation inspection, Final inspections (all subcodes).

§ 06

Frequently asked

Common questions about Burlington Township permits

01 Do I need a building permit in Burlington Township, NJ?
A construction permit is required for most work as per NJ Uniform Construction Code (UCC).
02 How much does a building permit cost in Burlington Township, NJ?
Building permit fees in Burlington Township, NJ are set by the local building department and vary by project type and valuation. The minimum permit fee is $70. Fees are calculated as: New Structures/Additions: $0.025 per cubic foot of building volume; Construction Trailer: $100 flat fee; Tent (under 900 sq ft): $70; Tent (over 900 sq ft or over 30 ft): $100; Roofing/Siding (Residential): $70 flat fee; Plumbing/Mechanical Fixtures: $25 per item (sinks, toilets, tubs, water heaters, dishwashers, vents, hose bibs, etc.).. Plan check fee: 25% of construction permit fee.
03 How do I apply for a building permit in Burlington Township, NJ?
To apply for a building permit in Burlington Township, NJ, follow these steps: 1. Visit Department of Licensing and Inspection to obtain application packet. 2. Complete NJ DCA UCC-F100 Construction Permit Application. 3. Submit three sets of plans for plan review. 4. Include site plan, construction drawings, specifications. 5. Provide contractor licenses and insurance certificates. 6. Pay plan review fee before review begins (25% of construction permit fee). 7. Submit documents in-person at Municipal Building. 8. Respond to plan review comments if required. 9. Pay remaining permit fees upon approval. 10. Obtain final permit and post on site before construction begins.
04 How long does it take to get a building permit in Burlington Township, NJ?
Building permit processing times in Burlington Township, NJ typically run Varies by project complexity; typically 2-4 weeks for plan review.. Timelines can vary based on project complexity and current department workload.
05 What work is exempt from building permits in Burlington Township, NJ?
Not all construction work requires a permit in Burlington Township, NJ. The following work is generally exempt: Ordinary repairs not involving code violations; Minor work as determined by subcode official and Construction Code Official; Emergency work (permit required within 72 hours); Cosmetic repairs; Non-structural maintenance. Note: Zoning approval may be required before construction permit issuance. All taxes and assessments must be current. Site plan approval may be required for certain projects. When in doubt, confirm with the local building department before starting work.
06 How do I schedule a building inspection in Burlington Township, NJ?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Burlington Township, NJ via: (609) 239-6412, Department of Licensing and Inspection. Contact Department of Licensing and Inspection..
last verified April 2026 entry id permits/new-jersey/burlington/burlington-township

Educational reference. Permit rules and fees change — confirm current requirements directly with Department of Licensing and Inspection before applying. Jaspector is not legal advice.

§   Adjacent

Other jurisdictions in Burlington County.

Same county, different permit office. Click for that jurisdiction's full guide.

All Burlington County jurisdictions →