When a permit is required
Permit triggers and exempt work for Mesquite
New construction, additions and alterations, commercial building work, wall construction over 4 feet high, retaining walls over 4 feet, swimming pools and spas, and most structural work
- Exempt Fences up to 6 feet in height (wood, chain link, vinyl, wrought iron)
Note: Zoning and other city codes still apply. Contact Building Division for additional exemptions.
- Completed permit application
- Plot plans (two copies)
- Construction plans/wall details
- Property line authorization if on shared property line
- Contractor license information
- Building code
- 2018 International Building Code (IBC) with Southern Nevada Amendments, 2018 International Residential Code (IRC), 2018 Uniform Plumbing Code (UPC), 2018 Uniform Mechanical Code (UMC), 2017 National Electrical Code (NEC), 2018 International Energy Conservation Code (IECC)
- Permit validity
- Contact department for specific timeframes
- Owner-builder
- Owners may act as owner-builder on their own property. Must comply with Nevada State Contractors Board requirements.
- Contractor requirements
- Nevada State Contractors Board license required for commercial work. Verification at https://www.nscb.nv.gov/
Source: City of Mesquite Building Division, Development Services ↗
Application process
Typical processing: 10-21 working days for plan review
- 01 Contact Building Division by calling (702) 346-2835 or visiting City Hall.
- 02 Prepare application package by completing required forms and plans.
- 03 Submit application in person at City Hall.
- 04 Pay submittal fee (e.g., $40 for wall permits, $1,000 for commercial building permits) at submission.
- 05 Plan review: staff reviews plans. Typical review time: 10-21 working days.
- 06 Permit issued upon approval and payment.
- 07 Schedule inspections.
Typical processing time: 10-21 working days for plan review
Source: City of Mesquite Building Division, Development Services ↗
Fee schedule
Mesquite building permit fees
Contact department for accepted payment methods
Required inspections
Scheduling and sequence
- (702) 346-2835 (phone)
- Inspection hours
- Contact department
Typical sequence: Typical inspection sequence: Foundation, framing, MEP rough-ins, insulation, drywall, final
Frequently asked
Common questions about Mesquite permits
01 Do I need a building permit in Mesquite, NV? ▸
02 How do I apply for a building permit in Mesquite, NV? ▸
03 How long does it take to get a building permit in Mesquite, NV? ▸
04 What work is exempt from building permits in Mesquite, NV? ▸
05 How do I schedule a building inspection in Mesquite, NV? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with City of Mesquite Building Division, Development Services before applying. Jaspector is not legal advice.