On this page 5
When a permit is required
Permit triggers and exempt work for Boulder City
New construction, additions and alterations, electrical, plumbing, and mechanical work, sign installation, and most building work
Note: Zoning and other city codes still apply. Contact Community Development Department for specific exemptions.
- Completed permit application
- Construction plans (sealed by design professional as required)
- Site plan
- Contractor license information
- Owner-builder affidavit if applicable
- Building code
- 2018 International Building Code (IBC) with Southern Nevada Amendments, 2018 International Residential Code (IRC), 2018 Uniform Plumbing Code (UPC), 2018 Uniform Mechanical Code (UMC), 2017 National Electrical Code (NEC), 2018 International Energy Conservation Code (IECC), 2018 International Fire Code (IFC)
- Permit validity
- Contact department for specific timeframes
- Owner-builder
- Owners may act as owner-builder on their own property. Must comply with Nevada State Contractors Board requirements.
- Contractor requirements
- Nevada State Contractors Board license required. Verification at https://www.nscb.nv.gov/
Source: Boulder City Community Development Department, Building and Safety Division ↗
Application process
Typical processing: Contact department for current timeframes
- 01 Contact Community Development by calling (702) 293-9282 or visiting office to discuss project.
- 02 Prepare application and plans by completing building permit application and preparing required plans.
- 03 Submit application in person or by mail to Community Development Department.
- 04 Plan review: staff reviews for code compliance.
- 05 Pay fees upon approval.
- 06 Permit issued.
- 07 Schedule inspections by calling the department.
Typical processing time: Contact department for current timeframes
Source: Boulder City Community Development Department, Building and Safety Division ↗
Required inspections
Scheduling and sequence
- (702) 293-9282 (phone)
- Visit office (in-person)
- Inspection hours
- Contact department
Typical sequence: Typical inspection sequence: Foundation, framing, MEP rough-ins, insulation, drywall, final
Frequently asked
Common questions about Boulder City permits
01 Do I need a building permit in Boulder City, NV? ▸
02 How do I apply for a building permit in Boulder City, NV? ▸
03 How long does it take to get a building permit in Boulder City, NV? ▸
04 How do I schedule a building inspection in Boulder City, NV? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with Boulder City Community Development Department, Building and Safety Division before applying. Jaspector is not legal advice.