When a permit is required
Permit triggers and exempt work for McCook
All construction, alteration, repair, or demolition of buildings in City of McCook requires a building permit
- Completed permit application
- Site plan showing structure location and dimensions
- Setbacks from property lines and street rights-of-way
- Construction plans (as applicable)
- Current City of McCook contractor licenses for all contractors
- Building code
- McCook has adopted building codes based on 2018 International Building Code (IBC) and 2018 International Residential Code (IRC), consistent with Nebraska state building code, with local amendments to IRC sections on temporary power, automatic fire sprinkler systems, footings for frost protection, and truss design drawings. Complete municipal code (Chapter 150 — Building Codes and Regulations) available through American Legal Publishing: https://codelibrary.amlegal.com/codes/mccook/latest/mccook_ne/0-0-0-1
- Contractor requirements
- Any contractor performing work in City of McCook must hold a current City of McCook contractor license before a building permit will be issued. License types: General Contractor ($200 new/$100 renewal), Building Contractor ($180/$90), Residential Contractor ($150/$75), Plumbing Contractor ($150/$75), Mechanical/HVAC Contractor ($150/$75), Roofing Contractor ($120/$60), Limited Contractor ($120/$60). All licenses valid January 1–December 31 annually. Insurance requirement: $1,000,000 per occurrence liability insurance with City of McCook as certificate holder. No bond required. Proof of experience required for new applications.
Application process
Application → plan check → issuance → inspection → final
- 01 Confirm project location is within McCook corporate limits or within extraterritorial jurisdiction (2 miles beyond city limits)
- 02 Download applicable permit application(s) from city website; separate permit required for each building or structure
- 03 Prepare required documents: completed application, site plan showing location/dimensions, setbacks, and construction plans as applicable
- 04 Ensure all contractors hold current City of McCook contractor licenses before submission
- 05 Submit completed application with applicable fee to Building and Zoning Department at 505 W C Street
- 06 Building Inspector reviews for compliance with McCook building codes and zoning ordinance
- 07 Upon approval, building permit is issued; no construction may begin until permit is in hand
- 08 Call Barry Mooney at (308) 345-2022 ext. 232 or (308) 340-9694 to schedule required inspections
- 09 For commercial and public-assembly projects, submit plans to Nebraska State Fire Marshal concurrently or prior to city permit process
- 10 After work completion and final inspection approval, project is closed
Fee schedule
Effective 2023-03-06
Fees change periodically. Confirm at the official fee schedule ↗ (effective 2023-03-06) before budgeting.
Required inspections
Scheduling and sequence
- Contact Building Inspector Barry Mooney directly (phone)
- Phone: (308) 345-2022, ext. 232 (phone)
- Cell: (308) 340-9694 (phone)
- Email: bldginsp@cityofmccook.com (email)
- Inspection hours
- Monday–Friday, 7:30 AM–4:30 PM
Typical sequence: McCook conducts building inspections at key stages of construction: building, foundation, framing, plumbing, mechanical, and final inspections. Commercial and public-assembly projects are also subject to Nebraska State Fire Marshal inspection.
Frequently asked
Common questions about McCook permits
01 Do I need a building permit in McCook, NE? ▸
02 How much does a building permit cost in McCook, NE? ▸
03 How do I apply for a building permit in McCook, NE? ▸
04 How do I schedule a building inspection in McCook, NE? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with City of McCook — Building and Zoning Department before applying. Jaspector is not legal advice.