Permit authority

City of Ralston Building and Safety Division

Street address
5500 S. 77th Street, Ralston, NE 68127 (City Hall)
Coverage
All properties within the incorporated limits of the City of Ralston. Ralston is an independent second-class city within Douglas County and administers its own building permit program separately from Omaha and Douglas County.
Online portal
SmartGov Community
SmartGov Community
§ 02

When a permit is required

Permit triggers and exempt work for Ralston

Required for most construction projects including new buildings, additions, structural alterations, electrical work, plumbing, mechanical, and other regulated work per adopted codes.

Note: Not published as a standalone list. Under adopted 2018 IRC/IBC, common exemptions generally include minor repair work, painting, papering, tiling, carpeting, flooring, cabinets, counter tops, and similar finish work. Specific exemption list should be confirmed directly with City of Ralston Building and Safety Division at (402) 331-6677 Ext. 1310.

Required documents
  • Completed permit application
  • Construction plans and drawings
  • Site plan
  • Contractor licensing information
  • Plumbing license application available through portal for licensed plumbers
Building code
2018 International Building Code (IBC); 2018 International Residential Code (IRC); 2021 Ralston Plumbing Code; 2023 National Electrical Code (NEC); 2018 International Mechanical Code (IMC); 2018 International Energy Conservation Code (IECC); 2018 International Swimming Pool and Spa Code; 2018 International Property Maintenance Code
Permit validity
Work must begin within 180 days of issuance and be substantially completed within two years. Work cannot be abandoned for six months during construction.
Owner-builder
Not specifically published. Contact Building Director for owner-builder guidance.
Contractor requirements
Contractors must hold appropriate licenses. Ralston follows adopted codes including contractor licensing provisions. Contact Building Director at (402) 331-6677 Ext. 1310 for specific requirements.
§ 03

Application process

Typical processing: Not published. Contact (402) 331-6677 Ext. 1310 for current timeline.

  1. 01
    Determine whether the project requires a permit under Ralston's adopted codes.
  2. 02
    For paper application, contact Building Director at dfreshman@cityofralston.com or visit City Hall.
  3. 03
    For online application, register or log in at https://ci-ralston-ne.smartgovcommunity.com/.
  4. 04
    Complete application with project description, site information, and contractor details.
  5. 05
    Upload or submit required drawings and documentation.
  6. 06
    Application reviewed by City of Ralston Building and Safety Division.
  7. 07
    Receive notification of approval or request for additional information.
  8. 08
    Pay required fees.
  9. 09
    Permit issued; post on job site.
  10. 10
    Schedule required inspections through the portal or by contacting the Building Director.
  11. 11
    Pass all required inspections; final approval issued.

Typical processing time: Not published. Contact (402) 331-6677 Ext. 1310 for current timeline.

Source: City of Ralston Building and Safety Division ↗

§ 04

Required inspections

Scheduling and sequence

How to schedule
Inspection hours
Contact Building Director for inspection scheduling windows.

Typical sequence: Standard IBC/IRC sequence -- foundation, framing, rough-in (electrical, plumbing, mechanical), insulation, final.

§ 05

Frequently asked

Common questions about Ralston permits

01 Do I need a building permit in Ralston, NE?
Required for most construction projects including new buildings, additions, structural alterations, electrical work, plumbing, mechanical, and other regulated work per adopted codes.
02 How do I apply for a building permit in Ralston, NE?
To apply for a building permit in Ralston, NE, follow these steps: 1. Determine whether the project requires a permit under Ralston's adopted codes. 2. For paper application, contact Building Director at dfreshman@cityofralston.com or visit City Hall. 3. For online application, register or log in at https://ci-ralston-ne.smartgovcommunity.com/. 4. Complete application with project description, site information, and contractor details. 5. Upload or submit required drawings and documentation. 6. Application reviewed by City of Ralston Building and Safety Division. 7. Receive notification of approval or request for additional information. 8. Pay required fees. 9. Permit issued; post on job site. 10. Schedule required inspections through the portal or by contacting the Building Director. 11. Pass all required inspections; final approval issued.
03 How long does it take to get a building permit in Ralston, NE?
Building permit processing times in Ralston, NE typically run Not published. Contact (402) 331-6677 Ext. 1310 for current timeline.. Timelines can vary based on project complexity and current department workload.
04 How do I schedule a building inspection in Ralston, NE?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Ralston, NE via: SmartGov portal, (402) 331-6677, Ext. 1310.
last verified April 2026 source City of Ralston Building and Safety Division ↗ entry id permits/nebraska/douglas/ralston

Educational reference. Permit rules and fees change — confirm current requirements directly with City of Ralston Building and Safety Division before applying. Jaspector is not legal advice.

§   Adjacent

Other jurisdictions in Douglas County.

Same county, different permit office. Click for that jurisdiction's full guide.

All Douglas County jurisdictions →