City of Brandon

How to apply for a building permit in City of Brandon, Mississippi. Permit authority, application steps, fees, and inspection requirements.

Last verified
April 2026
On this page 6
§ 01

Permit authority

Community Development Department

Street address
1000 Municipal Drive, Brandon, MS 39042
Coverage
Covers all property within the incorporated city limits of Brandon. Unincorporated Rankin County property adjacent to Brandon falls under the county's jurisdiction.
Additional resources
§ 02

When a permit is required

Permit triggers and exempt work for Brandon

New construction, additions, remodeling, and repairs to electrical, mechanical, and plumbing systems

Note: No specific public list identified. General exemptions under adopted 2018 IBC apply; cosmetic work (painting, flooring, cabinetry without structural changes) typically exempt. Confirm with Community Development at 601-824-4580.

Required documents
  • Building permit application
  • Construction plans
  • Contractor information
Building code
2018 International Building Code (with amendments); 2018 International Property Maintenance Code (with amendments)
Permit validity
Permits expire after 90 days if no inspections have been conducted. Extension requests must be submitted in writing to the Community Development Director.
Contractor requirements
MSBOC licensure required for applicable project thresholds; confirm current requirements with the department
§ 03

Application process

Application → plan check → issuance → inspection → final

  1. 01
    Contact the Community Development Department at 601-824-4580 or jbarnette@brandonms.org to confirm permit requirements.
  2. 02
    Download or obtain the building permit application (referenced at the permits page and available as a PDF).
  3. 03
    Prepare required plans and supporting documents.
  4. 04
    Submit application in person at 1000 Municipal Drive.
  5. 05
    Plans are reviewed for compliance with the 2018 International Building Code and other adopted codes.
  6. 06
    If additional information is required, the application is placed on hold; the applicant is notified to provide fee receipts, certificates, calculations, or revised drawings.
  7. 07
    Permit is issued upon approval.
  8. 08
    Schedule and complete required inspections as work progresses.
  9. 09
    Obtain final inspection sign-off and Certificate of Occupancy.

Source: Community Development Department ↗

§ 04

Fee schedule

Effective July 1, 2025

Fee type
Amount
01
Plan check fee
May apply
02
Permit fee formula
Valuation-based per Schedule A (effective July 1, 2025 version referenced in search results)

In-person payment at Community Development office; hours 8:00 AM to 5:00 PM Monday through Friday

Fees change periodically. Confirm at the official fee schedule ↗ (effective July 1, 2025) before budgeting.

§ 05

Required inspections

Scheduling and sequence

How to schedule
  • 601-824-4580 (phone)
Inspection hours
Monday through Friday, 8:00 AM to 5:00 PM

Typical sequence: Varies by project type; includes foundation, rough-in (electrical, plumbing, mechanical), and final inspection leading to Certificate of Occupancy

§ 06

Frequently asked

Common questions about Brandon permits

01 Do I need a building permit in Brandon, MS?
New construction, additions, remodeling, and repairs to electrical, mechanical, and plumbing systems
02 How much does a building permit cost in Brandon, MS?
Building permit fees in Brandon, MS are set by the local building department and vary by project type and valuation. Fees are calculated as: Valuation-based per Schedule A (effective July 1, 2025 version referenced in search results). Plan check fee: May apply.
03 How do I apply for a building permit in Brandon, MS?
To apply for a building permit in Brandon, MS, follow these steps: 1. Contact the Community Development Department at 601-824-4580 or jbarnette@brandonms.org to confirm permit requirements. 2. Download or obtain the building permit application (referenced at the permits page and available as a PDF). 3. Prepare required plans and supporting documents. 4. Submit application in person at 1000 Municipal Drive. 5. Plans are reviewed for compliance with the 2018 International Building Code and other adopted codes. 6. If additional information is required, the application is placed on hold; the applicant is notified to provide fee receipts, certificates, calculations, or revised drawings. 7. Permit is issued upon approval. 8. Schedule and complete required inspections as work progresses. 9. Obtain final inspection sign-off and Certificate of Occupancy.
04 How do I schedule a building inspection in Brandon, MS?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Brandon, MS via: 601-824-4580.
last verified April 2026 source Community Development Department ↗ entry id permits/mississippi/rankin/brandon

Educational reference. Permit rules and fees change — confirm current requirements directly with Community Development Department before applying. Jaspector is not legal advice.