How to apply for a building permit in City of Brookhaven, Mississippi. Permit authority, application steps, fees, and inspection requirements.

Avg processing
2 weeks
Last verified
April 2026
On this page 5
§ 01

Permit authority

City Building Inspector's Office

Street address
301 South 1st Street, Room 102, Brookhaven, MS 39601
Coverage
All properties within the incorporated City of Brookhaven.
Additional resources
§ 02

When a permit is required

Permit triggers and exempt work for Brookhaven

A building permit is required for new residential, commercial, or industrial construction, additions or alterations to existing structures, demolition work, repairs that affect structural integrity or fire safety, installation of mechanical, electrical, or plumbing systems, and septic system installation or repair.

Required documents
  • Completed building permit application form
  • 2 sets of detailed building plans
  • Property deed
Building code
2003 International Fire Code; general building code requirements per Brookhaven Municipal Ordinances, including Ordinance 143
§ 03

Application process

Typical processing: 2 weeks

  1. 01
    Obtain building permit application form from the City Building Inspector's office or website.
  2. 02
    Prepare 2 sets of detailed building plans with all required specifications.
  3. 03
    Provide a copy of the property deed.
  4. 04
    Complete all sections of the permit application.
  5. 05
    Submit application and plans to the City Building Inspector, Room 102.
  6. 06
    Allow a 2-week review period for plan examination.
  7. 07
    Upon approval, pay permit fees.
  8. 08
    Receive permit and schedule inspections.

Typical processing time: 2 weeks

Source: City Building Inspector's Office ↗

§ 04

Required inspections

Scheduling and sequence

How to schedule
  • 601-833-7766 (phone)

Typical sequence: Standard inspection stages: foundation/site inspection (pre-construction or early phase), framing inspection (structural phase), electrical/plumbing/mechanical rough-in inspection (systems phase), and final inspection (upon completion).

§ 05

Frequently asked

Common questions about Brookhaven permits

01 Do I need a building permit in Brookhaven, MS?
A building permit is required for new residential, commercial, or industrial construction, additions or alterations to existing structures, demolition work, repairs that affect structural integrity or fire safety, installation of mechanical, electrical, or plumbing systems, and septic system installation or repair.
02 How do I apply for a building permit in Brookhaven, MS?
To apply for a building permit in Brookhaven, MS, follow these steps: 1. Obtain building permit application form from the City Building Inspector's office or website. 2. Prepare 2 sets of detailed building plans with all required specifications. 3. Provide a copy of the property deed. 4. Complete all sections of the permit application. 5. Submit application and plans to the City Building Inspector, Room 102. 6. Allow a 2-week review period for plan examination. 7. Upon approval, pay permit fees. 8. Receive permit and schedule inspections.
03 How long does it take to get a building permit in Brookhaven, MS?
Building permit processing times in Brookhaven, MS typically run 2 weeks. Timelines can vary based on project complexity and current department workload.
04 How do I schedule a building inspection in Brookhaven, MS?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Brookhaven, MS via: 601-833-7766.
last verified April 2026 source City Building Inspector's Office ↗ entry id permits/mississippi/lincoln/brookhaven

Educational reference. Permit rules and fees change — confirm current requirements directly with City Building Inspector's Office before applying. Jaspector is not legal advice.

§   Adjacent

Other jurisdictions in Lincoln County.

Same county, different permit office. Click for that jurisdiction's full guide.

All Lincoln County jurisdictions →