When a permit is required
Permit triggers and exempt work for Lincoln County
A building permit is required for new construction, repairs, demolition, septic system installation or repair, and any work that must demonstrate compliance with fire codes and building codes.
- Exempt Agricultural structures as exempted by Mississippi state law (verify with Chancery Clerk)
Note: Mississippi state law may exempt certain agricultural structures from permit requirements. Verify applicability with the Lincoln County Chancery Clerk before proceeding.
- Completed building permit application form
- 2 sets of building plans
- Property deed
- Building code
- 2019 International Building Code plus state amendments
Application process
Typical processing: 2 weeks
- 01 Contact the Lincoln County Chancery Clerk's office at 601-835-3411 for application forms and specific requirements.
- 02 Prepare 2 sets of building plans with all required specifications.
- 03 Provide a copy of the property deed.
- 04 Complete the building permit application form.
- 05 Submit all documents to the Lincoln County Chancery Clerk at 301 S First Street, Rm 111, Brookhaven, MS 39601.
- 06 Allow approximately 2 weeks for plan review and processing.
- 07 Receive permit and pay applicable fees upon approval.
Typical processing time: 2 weeks
Fee schedule
Lincoln County building permit fees
Contact the Lincoln County Chancery Clerk's office at 601-835-3411 for specific fee quotes based on project scope and construction value.
Required inspections
Scheduling and sequence
- 601-835-3411 (phone)
Typical sequence: Required inspection stages include: foundation inspection, framing inspection, electrical/mechanical/plumbing rough-in inspection, and final inspection upon completion.
Frequently asked
Common questions about unincorporated Lincoln County permits
01 Do I need a building permit in unincorporated Lincoln County, MS? ▸
02 How much does a building permit cost in unincorporated Lincoln County, MS? ▸
03 How do I apply for a building permit in unincorporated Lincoln County, MS? ▸
04 How long does it take to get a building permit in unincorporated Lincoln County, MS? ▸
05 What work is exempt from building permits in unincorporated Lincoln County, MS? ▸
06 How do I schedule a building inspection in unincorporated Lincoln County, MS? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with Lincoln County Chancery Clerk before applying. Jaspector is not legal advice.