When a permit is required
Permit triggers and exempt work for Hatton Township
County permits required for regulated projects.
- Completed county permit form
- Project information and contact details
- Building code
- State Building Code, Michigan Electrical Code, State Plumbing Code, Michigan Building Code / Michigan Residential Code
- Permit validity
- Permit invalid if work does not start within six months or is suspended/abandoned for six months.
- Owner-builder
- Owner-builder may be permit holder via county process.
- Contractor requirements
- Use licensed and insured trades where required.
Application process
Application → plan check → issuance → inspection → final
- 01 Submit county permit application for regulated work.
- 02 Contact Hatton Township for local zoning details.
Fee schedule
Hatton Township building permit fees
Work started before permit issuance may double total permit fees on trade forms.
Required inspections
Scheduling and sequence
- County inspection line 989-539-2741 (phone)
- County inspection fax 989-539-7385 (fax)
- Scheduling deadline
- Most inspections are completed within three business days after request.
- Inspection hours
- 8:00 a.m. through 4:30 p.m.
Typical sequence: Permit holder provides permit number, site address, township/city, and contact phone for scheduling details.
Frequently asked
Common questions about Hatton Township permits
01 Do I need a building permit in Hatton Township, MI? ▸
02 How much does a building permit cost in Hatton Township, MI? ▸
03 How do I apply for a building permit in Hatton Township, MI? ▸
04 How do I schedule a building inspection in Hatton Township, MI? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with Clare County Community Development before applying. Jaspector is not legal advice.