On this page 6
When a permit is required
Permit triggers and exempt work for Greenwood Township
County permits apply for building, electrical, plumbing, and mechanical work.
- Completed county permit application
- Trade-specific permit requirements
- Building code
- State Building Code, Michigan Electrical Code, State Plumbing Code, Michigan Building Code / Michigan Residential Code
- Permit validity
- Permit invalid if work does not start within six months or is suspended/abandoned for six months.
- Owner-builder
- Owner-builder permitted as applicable on county application.
- Contractor requirements
- Licensed and insured trades required where required.
Application process
Application → plan check → issuance → inspection → final
- 01 Submit county permit forms for regulated construction work.
- 02 Coordinate zoning with Greenwood Township when needed.
Fee schedule
Greenwood Township building permit fees
Work started before permit issuance may double total permit fees on trade forms.
Required inspections
Scheduling and sequence
- County inspection line 989-539-2741 (phone)
- County inspection fax 989-539-7385 (fax)
- Scheduling deadline
- Most inspections are completed within three business days after request.
- Inspection hours
- 8:00 a.m. through 4:30 p.m.
Typical sequence: First-requested, first-scheduled basis.
Frequently asked
Common questions about Greenwood Township permits
01 Do I need a building permit in Greenwood Township, MI? ▸
02 How much does a building permit cost in Greenwood Township, MI? ▸
03 How do I apply for a building permit in Greenwood Township, MI? ▸
04 How do I schedule a building inspection in Greenwood Township, MI? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with Clare County Community Development before applying. Jaspector is not legal advice.