How to apply for a building permit in St. Charles, Maryland. Permit authority, application steps, fees, and inspection requirements.

Last verified
April 2026
On this page 6
§ 01

Permit authority

Charles County Department of Planning and Growth Management, Codes, Permits, and Inspection Services

Street address
200 Baltimore Street, La Plata, MD 20646
Coverage
St. Charles is not an incorporated municipality; permits are county-administered. Public county FAQ notes that properties in Planned Unit Development zoning must obtain Planning Design Review Board approval from Meredith Management for sign permits. Private community covenants may add additional non-county approvals.
Online portal
Citizen Self Service (CSS)
EnerGov
§ 02

When a permit is required

Permit triggers and exempt work for St. Charles

County residential and commercial permit triggers apply. For sign permits in PUD-zoned properties, County FAQ requires Planning Design Review Board approval from Meredith Management at 301-843-8111 before application submission.

Note: County public examples of exempt work are project-specific and should be confirmed with the Permit Center.

Required documents
  • County-required plans and supporting documents
  • Any PUD or private design approval that applies to the St. Charles parcel and project type
Building code
Charles County 2021 I-Codes and 2020 NEC for permits applied for on or after June 28, 2024.
Permit validity
Verify on issued permit for expiration terms. County extension fee schedule is public.
Owner-builder
County owner-contractor and homeowner electrical rules apply. Owners may serve as their own general contractor and assume liability. Homeowners may perform limited electrical work unless they obtain a Homeowner Permit.
Contractor requirements
Maryland State Contractors License, Maryland State Home Improvement License, or Maryland Home Improvement Commission license as applicable. Electrical work requires an active Maryland Master Electrician license or Charles County restricted master license with current insurance on file.

Source: Charles County Department of Planning and Growth Management, Codes, Permits, and Inspection Services ↗

§ 03

Application process

Typical processing: Acceptance within 2 business days; residential review 6 business days; Critical Area residential review 8 business days; commercial review 15 business days; trade permits 2 business days.

  1. 01
    Verify project zoning and any St. Charles PUD or private design-control requirements before filing.
  2. 02
    Create a CSS account and submit the county permit application with required plans and documents.
  3. 03
    Pay initial application and review fees after County acceptance.
  4. 04
    Respond to County review comments and resubmit as needed.
  5. 05
    If the property is in a PUD-controlled area, provide required Planning Design Review Board (PDRB) approval where the permit type requires it.
  6. 06
    Receive issued permit electronically through CSS.
  7. 07
    Complete all required inspections before final approval or occupancy.

Typical processing time: Acceptance within 2 business days; residential review 6 business days; Critical Area residential review 8 business days; commercial review 15 business days; trade permits 2 business days.

Source: Charles County Department of Planning and Growth Management, Codes, Permits, and Inspection Services ↗

§ 04

Fee schedule

Effective FY26

Fee type
Amount
01
Minimum permit fee
$144 for new construction/additions/alterations; $115 for other building/zoning/critical area permits; $27 each for trade permits
02
Plan check fee
$0.19 per square foot for residential (minimum $139); $0.19 per square foot for commercial (minimum $222)
03
Permit fee formula
Mixed schedule by permit type, square footage, and review type
04
Trade permit fee
$27 per trade permit
05
Reinspection fee
$158 for building or trade reinspection
06
Penalty (no permit)
Stop work and code violation fees apply

Pay through County CSS or at Treasury payment centers. Any PUD/private review costs are separate from County permit fees.

Fees change periodically. Confirm at the official fee schedule ↗ (effective FY26) before budgeting.

§ 05

Required inspections

Scheduling and sequence

How to schedule
Scheduling deadline
Contact the appropriate inspection agency per the Schedule an Inspection page.
Inspection hours
Monday–Friday, 8:00 AM to 4:30 PM

Typical sequence: Permit-specific sequence listed on the issued County permit. Building, trade, and fire safety inspections are coordinated through PlanChek.

Source: Charles County Department of Planning and Growth Management, Codes, Permits, and Inspection Services ↗

§ 06

Frequently asked

Common questions about St. Charles permits

01 Do I need a building permit in St. Charles, MD?
County residential and commercial permit triggers apply. For sign permits in PUD-zoned properties, County FAQ requires Planning Design Review Board approval from Meredith Management at 301-843-8111 before application submission.
02 How much does a building permit cost in St. Charles, MD?
Building permit fees in St. Charles, MD are set by the local building department and vary by project type and valuation. The minimum permit fee is $144 for new construction/additions/alterations; $115 for other building/zoning/critical area permits; $27 each for trade permits. Fees are calculated as: Mixed schedule by permit type, square footage, and review type. Plan check fee: $0.19 per square foot for residential (minimum $139); $0.19 per square foot for commercial (minimum $222).
03 How do I apply for a building permit in St. Charles, MD?
To apply for a building permit in St. Charles, MD, follow these steps: 1. Verify project zoning and any St. Charles PUD or private design-control requirements before filing. 2. Create a CSS account and submit the county permit application with required plans and documents. 3. Pay initial application and review fees after County acceptance. 4. Respond to County review comments and resubmit as needed. 5. If the property is in a PUD-controlled area, provide required Planning Design Review Board (PDRB) approval where the permit type requires it. 6. Receive issued permit electronically through CSS. 7. Complete all required inspections before final approval or occupancy.
04 How long does it take to get a building permit in St. Charles, MD?
Building permit processing times in St. Charles, MD typically run Acceptance within 2 business days; residential review 6 business days; Critical Area residential review 8 business days; commercial review 15 business days; trade permits 2 business days.. Timelines can vary based on project complexity and current department workload.
05 How do I schedule a building inspection in St. Charles, MD?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in St. Charles, MD via: Schedule an Inspection page, 301-645-0692. Contact the appropriate inspection agency per the Schedule an Inspection page..

Educational reference. Permit rules and fees change — confirm current requirements directly with Charles County Department of Planning and Growth Management, Codes, Permits, and Inspection Services before applying. Jaspector is not legal advice.