§ 01

Permit authority

Town of Porter -- Code Enforcement Office

Street address
Porter Town Office, Porter, ME 04068 (contact office for street address)
Coverage
Porter is a small Oxford County town well below the 4,000-person MUBEC threshold. CEO Dan Davis serves by appointment; office hours are by appointment only -- email is preferred. The CEO administers and enforces the Land Use Ordinance, reviews plans, conducts inspections, and supports the Planning Board and Appeals Board. Several state-level notifications may be required depending on project scope (Maine DEP, Maine Forest Service, Saco River Corridor Commission).
Online portal
Permit portal
Municipal website (PDF forms)
§ 02

When a permit is required

Permit triggers and exempt work for Porter

Per the Porter Land Use Ordinance (April 7, 2021 revision); construction, placement, or alteration of structures. Pre-built shed placement requires prior contact with CEO.

Per local Land Use Ordinance; contact CEO for details.
  • Exempt Per local Land Use Ordinance; contact CEO for details.
Required documents
  • Land Use Permit Application
  • site plan
  • applicable construction information. Floodplain permits for applicable zones
  • Access Permit (formerly Driveway Permit)
  • Demolition Permit as applicable.
Building code
Local Land Use Ordinance; MUBEC enforcement voluntary as population is below 4,000.
Contractor requirements
No general contractor state license required. Maine state licenses required for electricians and plumbers. State-level permits from Maine DEP, Maine Forest Service, or Saco River Corridor Commission may be required depending on project location and scope.
§ 03

Application process

Application → plan check → issuance → inspection → final

  1. 01
    Email CEO Dan Davis at ceo@portermaine.org or leave a voicemail at (207) 256-4522 to discuss permit requirements and schedule appointment.
  2. 02
    Download and complete the Land Use Permit Application (or Building Permit Application as applicable) from the code enforcement page.
  3. 03
    If placing a pre-built shed, contact CEO prior to placement.
  4. 04
    Submit completed application with supporting documents at appointment.
  5. 05
    Fee assessed per the Consolidated Fees document (amended February 8, 2023); pay fee.
  6. 06
    Permit issued; begin work.
  7. 07
    Coordinate required inspections with CEO. - Processing time estimate if available: Not published; contact CEO. - Source URL: https://portermaine.org/code-enforcement

Source: Town of Porter -- Code Enforcement Office ↗

§ 04

Fee schedule

Porter building permit fees

Fee type
Amount
01
Minimum permit fee
See Consolidated Fees document.
02
Permit fee formula
Per Consolidated Fees document.
§ 05

Required inspections

Scheduling and sequence

How to schedule
  • 207 (phone)

Typical sequence: Per Land Use Ordinance; contact CEO for stage-specific requirements.

§ 06

Frequently asked

Common questions about Porter permits

01 Do I need a building permit in Porter, ME?
Per the Porter Land Use Ordinance (April 7, 2021 revision); construction, placement, or alteration of structures. Pre-built shed placement requires prior contact with CEO.
02 How much does a building permit cost in Porter, ME?
Building permit fees in Porter, ME are set by the local building department and vary by project type and valuation. The minimum permit fee is See Consolidated Fees document.. Fees are calculated as: Per Consolidated Fees document..
03 How do I apply for a building permit in Porter, ME?
To apply for a building permit in Porter, ME, follow these steps: 1. Email CEO Dan Davis at ceo@portermaine.org or leave a voicemail at (207) 256-4522 to discuss permit requirements and schedule appointment. 2. Download and complete the Land Use Permit Application (or Building Permit Application as applicable) from the code enforcement page. 3. If placing a pre-built shed, contact CEO prior to placement. 4. Submit completed application with supporting documents at appointment. 5. Fee assessed per the Consolidated Fees document (amended February 8, 2023); pay fee. 6. Permit issued; begin work. 7. Coordinate required inspections with CEO. - Processing time estimate if available: Not published; contact CEO. - Source URL: https://portermaine.org/code-enforcement
04 What work is exempt from building permits in Porter, ME?
Not all construction work requires a permit in Porter, ME. The following work is generally exempt: Per local Land Use Ordinance; contact CEO for details.. When in doubt, confirm with the local building department before starting work.
05 How do I schedule a building inspection in Porter, ME?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Porter, ME via: 207.
last verified April 2026 source Town of Porter -- Code Enforcement Office ↗ entry id permits/maine/oxford/porter

Educational reference. Permit rules and fees change — confirm current requirements directly with Town of Porter -- Code Enforcement Office before applying. Jaspector is not legal advice.