How to apply for a building permit in Town of Farmingdale, Maine. Permit authority, application steps, fees, and inspection requirements.

Avg processing
Not stated
Last verified
April 2026
On this page 6
§ 01

Permit authority

Code Enforcement (administered through Town Office)

Street address
289 Maine Avenue, Farmingdale, ME 04344
Coverage
Town of Farmingdale; all construction and land use within town limits
Online portal
None; downloadable forms (MS Word and PDF)
None; downloadable forms (MS Word and PDF)
§ 02

When a permit is required

Permit triggers and exempt work for Farmingdale

Per Farmingdale Code of Ordinances (updated 6-26-2024); new construction, additions, alterations, and other applicable work

Not explicitly listed; contact CEO
General Maine exemptions likely apply
  • Exempt Not explicitly listed; contact CEO
  • Exempt General Maine exemptions likely apply

Note: Exempt from building permit does not mean exempt from zoning and planning requirements. Confirm edge cases with the permitting office before proceeding.

Required documents
  • Building permit application
  • site plan
  • additional docs per project
Building code
Farmingdale is listed as a municipality that will enforce MUBEC; contact office for current adoption status

Source: Code Enforcement (administered through Town Office) ↗

§ 03

Application process

Typical processing: Not stated

  1. 01
    Contact town office at (207) 582-2225 to arrange appointment with Code Enforcement Officer
  2. 02
    Download building permit application (MS Word or PDF) from farmingdalemaine.org
  3. 03
    Complete application with site plan
  4. 04
    Submit in person at 289 Maine Ave
  5. 05
    Fee collected per Code of Ordinances fee schedule (Appendix 1)
  6. 06
    Permit issued; keep on site
  7. 07
    Inspections performed as necessary; additional fee applies for extra inspections needed due to work not ready

Typical processing time: Not stated

Source: Code Enforcement (administered through Town Office) ↗

§ 04

Fee schedule

Farmingdale building permit fees

Fee type
Amount
01
Minimum permit fee
Not explicitly listed in available sources
02
Permit fee formula
See Appendix 1 of Code of Ordinances
03
Reinspection fee
Additional fee required if extra inspection needed because work was not ready; see Appendix 1

Contact office

§ 05

Required inspections

Scheduling and sequence

How to schedule
  • (207) 582-2225 (phone)
Inspection hours
Monday, Tuesday, Thursday 7:30 AM-4:00 PM; Wednesday 10:00 AM-7:00 PM; Friday 7:30 AM-12:30 PM

Typical sequence: Inspections performed as necessary per permit conditions

Additional fee charged for extra inspections when work is not ready

Source: Code Enforcement (administered through Town Office) ↗

§ 06

Frequently asked

Common questions about Farmingdale permits

01 Do I need a building permit in Farmingdale, ME?
Per Farmingdale Code of Ordinances (updated 6-26-2024); new construction, additions, alterations, and other applicable work
02 How much does a building permit cost in Farmingdale, ME?
Building permit fees in Farmingdale, ME are set by the local building department and vary by project type and valuation. The minimum permit fee is Not explicitly listed in available sources. Fees are calculated as: See Appendix 1 of Code of Ordinances.
03 How do I apply for a building permit in Farmingdale, ME?
To apply for a building permit in Farmingdale, ME, follow these steps: 1. Contact town office at (207) 582-2225 to arrange appointment with Code Enforcement Officer 2. Download building permit application (MS Word or PDF) from farmingdalemaine.org 3. Complete application with site plan 4. Submit in person at 289 Maine Ave 5. Fee collected per Code of Ordinances fee schedule (Appendix 1) 6. Permit issued; keep on site 7. Inspections performed as necessary; additional fee applies for extra inspections needed due to work not ready
04 How long does it take to get a building permit in Farmingdale, ME?
Building permit processing times in Farmingdale, ME typically run Not stated. Timelines can vary based on project complexity and current department workload.
05 What work is exempt from building permits in Farmingdale, ME?
Not all construction work requires a permit in Farmingdale, ME. The following work is generally exempt: Not explicitly listed; contact CEO; General Maine exemptions likely apply. Note: Exempt from building permit does not mean exempt from zoning and planning requirements. Confirm edge cases with the permitting office before proceeding. When in doubt, confirm with the local building department before starting work.
06 How do I schedule a building inspection in Farmingdale, ME?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Farmingdale, ME via: (207) 582-2225.
last verified April 2026 source Code Enforcement (administered through Town Office) ↗ entry id permits/maine/kennebec/farmingdale